Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time–Cost Trade-Off Problem
Despite the importance of project deadlines and resource constraints in construction scheduling, very little success has been achieved in solving the resource-constrained discrete time–cost trade-off problem (RCDTCTP), especially for large-scale projects. In this paper a new heuristic method is designed and developed to achieve fast and high-quality solutions for the large-scale RCDTCTP. The proposed method is based on the novel principles to enable effective exploration of the search space through adequate selection of the activities to be crashed for a resource constrained schedule, by only crashing the activities with zero float in a resource constrained-schedule, which form the critical sequence. The computational experiment results reveal that the new critical sequence crashing heuristic outperforms the state-of-the-art methods, both in terms of the solution quality concerning project cost and computation time. Solutions with a deviation of 0.25% from the best known solutions are achieved within seconds for the first time, for a large-scale project including up to 2,000 activities. The main contribution of the new heuristic to practitioners and researchers is that it provides a fast and effective method for optimal scheduling of real-life-size construction projects with project deadlines and resource constraints.
Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time–Cost Trade-Off Problem
Despite the importance of project deadlines and resource constraints in construction scheduling, very little success has been achieved in solving the resource-constrained discrete time–cost trade-off problem (RCDTCTP), especially for large-scale projects. In this paper a new heuristic method is designed and developed to achieve fast and high-quality solutions for the large-scale RCDTCTP. The proposed method is based on the novel principles to enable effective exploration of the search space through adequate selection of the activities to be crashed for a resource constrained schedule, by only crashing the activities with zero float in a resource constrained-schedule, which form the critical sequence. The computational experiment results reveal that the new critical sequence crashing heuristic outperforms the state-of-the-art methods, both in terms of the solution quality concerning project cost and computation time. Solutions with a deviation of 0.25% from the best known solutions are achieved within seconds for the first time, for a large-scale project including up to 2,000 activities. The main contribution of the new heuristic to practitioners and researchers is that it provides a fast and effective method for optimal scheduling of real-life-size construction projects with project deadlines and resource constraints.
Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time–Cost Trade-Off Problem
Sonmez, Rifat (Autor:in) / Iranagh, Mahdi Abbasi (Autor:in) / Uysal, Furkan (Autor:in)
23.10.2015
Aufsatz (Zeitschrift)
Elektronische Ressource
Unbekannt
Critical Sequence Crashing Heuristic for Resource-Constrained Discrete Time–Cost Trade-Off Problem
Online Contents | 2016
|A crashing-based time-cost trade-off model considering quality cost and contract clauses
Taylor & Francis Verlag | 2021
|Taylor & Francis Verlag | 2024
|Emerald Group Publishing | 2020
|