Application of the Resource-Constrained Critical Path Method to Multiple Calendars and Progressed Schedules
This paper presents an application case study of the Resource-constrained Critical Path Method (RCPM). RCPM is a heuristic algorithm to identify resource-dependent activity relationships (resource links) during resource-constrained scheduling. Through resource links, the schedule provides reliable activity floats and the critical path, which traditional resource-constrained scheduling techniques hardly provide. A prototype RCPM system is developed based on the algorithm. The RCPM system is integrated with Primavera Project Planner (P3), so it imports the project data directly from a P3 project, performs required RCPM procedures, and updates the P3 project to establish an RCPM schedule. The system is also equipped with functions to handle PDM logic relationships, multiple calendars, and progressed schedules. This paper briefly reviews the key elements of the RCPM procedures and demonstrates how it can be applied to a P3 schedule that consists of multiple calendars and a progress stage. The presence of Phantom Float in P6 is also illustrated.
Application of the Resource-Constrained Critical Path Method to Multiple Calendars and Progressed Schedules
This paper presents an application case study of the Resource-constrained Critical Path Method (RCPM). RCPM is a heuristic algorithm to identify resource-dependent activity relationships (resource links) during resource-constrained scheduling. Through resource links, the schedule provides reliable activity floats and the critical path, which traditional resource-constrained scheduling techniques hardly provide. A prototype RCPM system is developed based on the algorithm. The RCPM system is integrated with Primavera Project Planner (P3), so it imports the project data directly from a P3 project, performs required RCPM procedures, and updates the P3 project to establish an RCPM schedule. The system is also equipped with functions to handle PDM logic relationships, multiple calendars, and progressed schedules. This paper briefly reviews the key elements of the RCPM procedures and demonstrates how it can be applied to a P3 schedule that consists of multiple calendars and a progress stage. The presence of Phantom Float in P6 is also illustrated.
Application of the Resource-Constrained Critical Path Method to Multiple Calendars and Progressed Schedules
de la Garza, Jesús M. (Autor:in) / Kim, Kyunghwan (Autor:in)
Construction Research Congress 2009 ; 2009 ; Seattle, Washington, United States
Building a Sustainable Future ; 916-925
01.04.2009
Aufsatz (Konferenz)
Elektronische Ressource
Englisch
British Library Conference Proceedings | 2009
|Critical Path Method with Multiple Calendars
Online Contents | 2005
|Critical Path Method with Multiple Calendars
British Library Online Contents | 2005
|Delay analysis in resource-constrained schedules
Online Contents | 2009
|Delay analysis in resource-constrained schedules
British Library Online Contents | 2009
|