Study of the Relationship between Procurement Duration and Project Performance in Design-Build Projects: Comparison between Water/Wastewater and Transportation Sectors
Previous studies on building, industrial, and transportation projects found that projects delivered using design-build tend to perform better than projects delivered with the traditional design-bid-build method. However, performance of design-build projects is affected by various factors, with procurement-related factors being among the most influential. Whereas other aspects of procurement have been largely investigated, the effect of procurement duration on project performance has been studied only for design-build transportation projects. In addition, few studies have focused specifically on the delivery of water/wastewater projects. This paper includes the results of a study on the relationship between procurement duration and performance of water/wastewater design-build projects. The study methodology was based on regression analysis of data from a sample of water/wastewater design-build projects. The results show that unlike the transportation sector, procurement duration has little effect on either schedule or cost performance in the water/wastewater sector. Likely reasons for this difference were then explored through a content analysis of procurement documents.
Study of the Relationship between Procurement Duration and Project Performance in Design-Build Projects: Comparison between Water/Wastewater and Transportation Sectors
Previous studies on building, industrial, and transportation projects found that projects delivered using design-build tend to perform better than projects delivered with the traditional design-bid-build method. However, performance of design-build projects is affected by various factors, with procurement-related factors being among the most influential. Whereas other aspects of procurement have been largely investigated, the effect of procurement duration on project performance has been studied only for design-build transportation projects. In addition, few studies have focused specifically on the delivery of water/wastewater projects. This paper includes the results of a study on the relationship between procurement duration and performance of water/wastewater design-build projects. The study methodology was based on regression analysis of data from a sample of water/wastewater design-build projects. The results show that unlike the transportation sector, procurement duration has little effect on either schedule or cost performance in the water/wastewater sector. Likely reasons for this difference were then explored through a content analysis of procurement documents.
Study of the Relationship between Procurement Duration and Project Performance in Design-Build Projects: Comparison between Water/Wastewater and Transportation Sectors
Bogus, Susan M. (Autor:in) / Migliaccio, Giovanni C. (Autor:in) / Jin, Ruoyu (Autor:in)
Journal of Management in Engineering ; 29 ; 382-391
07.01.2013
102013-01-01 pages
Aufsatz (Zeitschrift)
Elektronische Ressource
Englisch
Effect of Duration of Design-Build Procurement on Performance of Transportation Projects
British Library Online Contents | 2010
|Comparison Between Design-Build And Design-Bid-Build Transportation Projects Using Lane Mile Data
British Library Conference Proceedings | 2007
|Selecting appropriate projects for design-build procurement
British Library Conference Proceedings | 1999
|