Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Ground and tunnel deformation induced by excavation in pipe-roof pre-construction tunnel: A case study
Highlights The deformation characteristics of the pipe-roof pre-construction tunnel during the earth excavation phase are summarised. A method for calculating the deformation of the roof and floor of the pipe-roof pre-construction tunnel is proposed. The safety of the pipe-roof pre-construction tunnel during the earthwork excavation phase was assessed. The settlement law of the surface track in the excavation phase of the pipe screen pre-construction method was analysed.
Abstract The tunnel crossing project of Taiyuan Railway Station was constructed through the pipe-roof preconstruction method to minimise the disturbance of the construction to the railway station. Twenty 2 m-diameter steel pipe jacks each were used each ring in this method. The spacing between adjacent jacking pipes was 165–265 mm. To ensure the stability of the pipe-roof preconstruction tunnel and the normal operation of the train during the earthwork excavation process, the soil pressure on the outside of the tunnel, tunnel deformation, track settlement and strain, and reinforcement stresses in the concrete of the tunnel envelope were monitored. The monitoring results show that vertical deformation of −2.7 mm occurred in the tunnel roof during the excavation process. A horizontal deformation of ±0.6 mm on the left and right sides of the tunnel and vertical deformation of +1.38 mm on the tunnel floor were also observed. The strain in the concrete due to the excavation and the change in stress in the reinforcement were within the elastic range of the material, indicating that the deformation of the tunnel was safe. The tunnel deformations calculated by simplifying the tunnel roof and floor to the arch model were in good agreement with the measured results. The surface track settlement monitoring results indicate that a settlement difference of 1–4 mm was rapidly generated at the surface during the train passage after the earthwork. However, the settlement returned to the previous level after the train passed the monitoring point. The maximum surface settlement after soil reconsolidation and stabilisation was less than 0.5 mm. These results suggest that the earth excavation of the tunnel have little impact on the safe passage of trains. The findings of the research could provide importance reference for the tunnelling project with similar problems.
Ground and tunnel deformation induced by excavation in pipe-roof pre-construction tunnel: A case study
Highlights The deformation characteristics of the pipe-roof pre-construction tunnel during the earth excavation phase are summarised. A method for calculating the deformation of the roof and floor of the pipe-roof pre-construction tunnel is proposed. The safety of the pipe-roof pre-construction tunnel during the earthwork excavation phase was assessed. The settlement law of the surface track in the excavation phase of the pipe screen pre-construction method was analysed.
Abstract The tunnel crossing project of Taiyuan Railway Station was constructed through the pipe-roof preconstruction method to minimise the disturbance of the construction to the railway station. Twenty 2 m-diameter steel pipe jacks each were used each ring in this method. The spacing between adjacent jacking pipes was 165–265 mm. To ensure the stability of the pipe-roof preconstruction tunnel and the normal operation of the train during the earthwork excavation process, the soil pressure on the outside of the tunnel, tunnel deformation, track settlement and strain, and reinforcement stresses in the concrete of the tunnel envelope were monitored. The monitoring results show that vertical deformation of −2.7 mm occurred in the tunnel roof during the excavation process. A horizontal deformation of ±0.6 mm on the left and right sides of the tunnel and vertical deformation of +1.38 mm on the tunnel floor were also observed. The strain in the concrete due to the excavation and the change in stress in the reinforcement were within the elastic range of the material, indicating that the deformation of the tunnel was safe. The tunnel deformations calculated by simplifying the tunnel roof and floor to the arch model were in good agreement with the measured results. The surface track settlement monitoring results indicate that a settlement difference of 1–4 mm was rapidly generated at the surface during the train passage after the earthwork. However, the settlement returned to the previous level after the train passed the monitoring point. The maximum surface settlement after soil reconsolidation and stabilisation was less than 0.5 mm. These results suggest that the earth excavation of the tunnel have little impact on the safe passage of trains. The findings of the research could provide importance reference for the tunnelling project with similar problems.
Ground and tunnel deformation induced by excavation in pipe-roof pre-construction tunnel: A case study
Yang, Songsong (Autor:in) / Zhang, Dingwen (Autor:in) / Wang, Mei (Autor:in) / Li, Jiyang (Autor:in)
25.10.2022
Aufsatz (Zeitschrift)
Elektronische Ressource
Englisch
Optimization of excavation and support in pipe roof supported tunnel sections
Online Contents | 2006
|Optimization of excavation and support in pipe roof supported tunnel sections
British Library Online Contents | 2006
|Optimization of excavation and support in pipe roof supported tunnel sections
British Library Conference Proceedings | 2006
|