Suggestions for takt production subcontract clauses – a conceptual study
This study aims to provide a foundation for the development of subcontracts that suit takt production in construction.
This is a non-empiric conceptual study, which integrates takt production and general construction literature into new proposals for subcontract clauses suitable for takt production in construction. This study uses literature reviews, from which proposals regarding takt production viable subcontract clauses are conducted via logical reasoning.
A total of 13 proposals for takt production applicable subcontracts are provided in this study. The proposals emphasize detailed and collaborative planning, suitable payment methods and flexibility for takt plan modification.
Previous takt literature has not properly addressed the development of subcontracts for takt production, despite regular attempts to use subcontracting in takt production. This study aims to aid main contractors to create fair and suitable subcontracts, so that adhering to takt schedules could be more viable in practice. This study also acts as a foundation for further empirical studies regarding the subject.
Suggestions for takt production subcontract clauses – a conceptual study
This study aims to provide a foundation for the development of subcontracts that suit takt production in construction.
This is a non-empiric conceptual study, which integrates takt production and general construction literature into new proposals for subcontract clauses suitable for takt production in construction. This study uses literature reviews, from which proposals regarding takt production viable subcontract clauses are conducted via logical reasoning.
A total of 13 proposals for takt production applicable subcontracts are provided in this study. The proposals emphasize detailed and collaborative planning, suitable payment methods and flexibility for takt plan modification.
Previous takt literature has not properly addressed the development of subcontracts for takt production, despite regular attempts to use subcontracting in takt production. This study aims to aid main contractors to create fair and suitable subcontracts, so that adhering to takt schedules could be more viable in practice. This study also acts as a foundation for further empirical studies regarding the subject.
Suggestions for takt production subcontract clauses – a conceptual study
Keskiniva, Kimmo (Autor:in) / Saari, Arto (Autor:in) / Junnonen, Juha-Matti (Autor:in)
Construction Innovation ; 23 ; 425-442
18.02.2022
18 pages
Aufsatz (Zeitschrift)
Elektronische Ressource
Englisch
Indicators for Takt Production Performance Assessment—A Conceptual Study
DOAJ | 2023
|Studying the form: Potentially onerous clauses in Wimpey's subcontract form are revealed
British Library Online Contents | 1996
Contract claws: There are some potentially onerous clauses in Matthew Hall's subcontract form
British Library Online Contents | 1996
Managing Subcontract Detailing
British Library Conference Proceedings | 1993
|Managing Subcontract Detailing
British Library Conference Proceedings | 1993
|