Installation method for corridor bridge of large space steel structure
The invention discloses an installation method for a corridor bridge of a large space steel structure. Corridor bridge steel structures are made at home, and then are shipped to an overseas installation site through containers after the pre-assembly inspection is passed, and are finally lifted after the assembly. The method is characterized by comprising the following steps: a, preparation before the installation of the corridor bridge; b, floor assembly of an outer frame of the corridor bridge; c, lifting of a corridor bridge component. According to the installation method for the corridor bridge of the large space steel structure provided by the invention, a process that the corridor bridge steel structures are made at home, and then are shipped to an overseas installation site through containers after the pre-assembly inspection is passed, and are finally lifted after the assembly is completely applicable to an operating mode that an overseas steel structure project is made at home and constructed by overseas workers; furthermore, the installation of the corridor bridge meets an international steel structure installation standard; in addition, the installation method has the advantages of being orderly to construct and reliable in quality, the construction cost can be saved, and the construction period can be shortened.
Installation method for corridor bridge of large space steel structure
The invention discloses an installation method for a corridor bridge of a large space steel structure. Corridor bridge steel structures are made at home, and then are shipped to an overseas installation site through containers after the pre-assembly inspection is passed, and are finally lifted after the assembly. The method is characterized by comprising the following steps: a, preparation before the installation of the corridor bridge; b, floor assembly of an outer frame of the corridor bridge; c, lifting of a corridor bridge component. According to the installation method for the corridor bridge of the large space steel structure provided by the invention, a process that the corridor bridge steel structures are made at home, and then are shipped to an overseas installation site through containers after the pre-assembly inspection is passed, and are finally lifted after the assembly is completely applicable to an operating mode that an overseas steel structure project is made at home and constructed by overseas workers; furthermore, the installation of the corridor bridge meets an international steel structure installation standard; in addition, the installation method has the advantages of being orderly to construct and reliable in quality, the construction cost can be saved, and the construction period can be shortened.
Installation method for corridor bridge of large space steel structure
CAI JING (Autor:in) / ZHOU JIANJIAN (Autor:in) / LIU MIAN (Autor:in) / ZHOU JING (Autor:in)
03.06.2015
Patent
Elektronische Ressource
Englisch
IPC:
E01D
BRIDGES
,
Brücken
Large-span steel structure corridor unit type installation method
Europäisches Patentamt | 2024
|Large-span steel structure corridor integral installation construction equipment and technology
Europäisches Patentamt | 2022
|Steel strand installation method for overall space corridor lifting construction
Europäisches Patentamt | 2015
|Large-span steel structure corridor construction method
Europäisches Patentamt | 2024
|