Construction method for breaking pile head of cast-in-place pile with static expansion cracking
The invention discloses a construction method for breaking a pile head of a cast-in-place pile with static expansion cracking. The construction method comprises the following steps that S1, a full-length sleeve plastic pipe is sleeved on a main rib above a pile foundation design elevation line; S2, a cast-in-place pile reinforcement cage is placed into a pile hole, and a lifting ring is inserted in a proper position of the pile top to be used for later lifting the pile head; S3, a foundation pit is excavated, the positioning line is drawn along the pile foundation design elevation, and the drilling equipment is used for drilling a horizontal drilling hole along the positioning line; S4, after drilling is completed, hole cleaning is carried out by adopting high-pressure wind or water; S5, an expanding agent and water are mixed according to a proportion, the mixture is rapidly loaded into the drilling hole, the hole is sealed through a rubber plug to prevent the expanding agent from being sprayed out of the drilling hole; S6, a chemical reaction of the expanding agent is awaited to generate an expansion pressure to break the pile; and S7, after the chemical reaction of the expandingagent is completed, a steel wire rope penetrates through the pile top lifting ring, and the pile head is lifted by using a crane to lift the pile head. The construction method has the beneficial effects that the pile breaking work of the construction method is low in noise, and the influence on the surrounding environment is small.
一种静态胀裂破除钻孔灌注桩桩头的施工方法,包括如下步骤:步骤1:在桩基设计标高线以上的主筋上全长度套塑料管;步骤2:将灌注桩钢筋笼下放入桩孔内,在桩顶适当位置插入吊环以作后续吊离桩头之用;步骤3:开挖基坑,沿桩基设计标高画定位线,采用钻孔设备沿定位线开凿水平钻眼;步骤4:钻孔钻设完成后,采用高压风或水对钻孔进行清孔;步骤5:将膨胀剂与水按比例混合,快速装入钻孔并用橡胶塞进行封孔防止膨胀剂喷出钻孔;步骤6:等待膨胀剂的化学反应产生膨胀压力破桩;步骤7:等膨胀剂化学反应完成,在桩顶吊环内穿钢丝绳,并利用吊机起吊将桩头吊出。本发明的有益效果是:该施工方法破桩工作产生噪音少,对周边环境影响小。
Construction method for breaking pile head of cast-in-place pile with static expansion cracking
The invention discloses a construction method for breaking a pile head of a cast-in-place pile with static expansion cracking. The construction method comprises the following steps that S1, a full-length sleeve plastic pipe is sleeved on a main rib above a pile foundation design elevation line; S2, a cast-in-place pile reinforcement cage is placed into a pile hole, and a lifting ring is inserted in a proper position of the pile top to be used for later lifting the pile head; S3, a foundation pit is excavated, the positioning line is drawn along the pile foundation design elevation, and the drilling equipment is used for drilling a horizontal drilling hole along the positioning line; S4, after drilling is completed, hole cleaning is carried out by adopting high-pressure wind or water; S5, an expanding agent and water are mixed according to a proportion, the mixture is rapidly loaded into the drilling hole, the hole is sealed through a rubber plug to prevent the expanding agent from being sprayed out of the drilling hole; S6, a chemical reaction of the expanding agent is awaited to generate an expansion pressure to break the pile; and S7, after the chemical reaction of the expandingagent is completed, a steel wire rope penetrates through the pile top lifting ring, and the pile head is lifted by using a crane to lift the pile head. The construction method has the beneficial effects that the pile breaking work of the construction method is low in noise, and the influence on the surrounding environment is small.
一种静态胀裂破除钻孔灌注桩桩头的施工方法,包括如下步骤:步骤1:在桩基设计标高线以上的主筋上全长度套塑料管;步骤2:将灌注桩钢筋笼下放入桩孔内,在桩顶适当位置插入吊环以作后续吊离桩头之用;步骤3:开挖基坑,沿桩基设计标高画定位线,采用钻孔设备沿定位线开凿水平钻眼;步骤4:钻孔钻设完成后,采用高压风或水对钻孔进行清孔;步骤5:将膨胀剂与水按比例混合,快速装入钻孔并用橡胶塞进行封孔防止膨胀剂喷出钻孔;步骤6:等待膨胀剂的化学反应产生膨胀压力破桩;步骤7:等膨胀剂化学反应完成,在桩顶吊环内穿钢丝绳,并利用吊机起吊将桩头吊出。本发明的有益效果是:该施工方法破桩工作产生噪音少,对周边环境影响小。
Construction method for breaking pile head of cast-in-place pile with static expansion cracking
一种静态胀裂破除钻孔灌注桩桩头的施工方法
XIA LONG (Autor:in) / LIAO JIANJUN (Autor:in) / ZENG XIANCAI (Autor:in) / WANG CHUWEI (Autor:in) / FANG JUNJIE (Autor:in) / SHEN XINGCHENG (Autor:in) / LIU CHAO (Autor:in) / CHEN YALAN (Autor:in)
14.04.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Construction method for breaking pile head of cast-in-place pile
Europäisches Patentamt | 2024
|Cast-in-place pile structure facilitating pile head breaking and construction method
Europäisches Patentamt | 2023
|Construction method convenient for breaking pile head of cast-in-place pile
Europäisches Patentamt | 2022
|Pile head breaking auxiliary device for cast-in-place pile and pile head breaking method
Europäisches Patentamt | 2024
|Pile head breaking method for concrete cast-in-place pile
Europäisches Patentamt | 2024
|