Single-pile foundation for electric transmission line and method for manufacturing single-pile foundation
The invention discloses a single-pile foundation for an electric transmission line and a method for manufacturing the single-pile foundation, and belongs to the field of single-pile foundation manufacturing. The single-pile foundation comprises multiple connecting longitudinal ribs and a columnar pile body with at least four columnar embedded parts. The multiple connecting longitudinal ribs are located around the portions, outside a target end face, of the at least four columnar embedded parts. The multiple connecting longitudinal ribs are provided with binding structures. The target end faceof the columnar pile body is provided with an isolating layer, and the at least four columnar embedded parts penetrate through the isolating layer. Protection sleeves are arranged at the ends, on thetarget end face, of the at least four columnar embedded parts. The multiple connecting longitudinal ribs are provided with first metal net sheets. A concrete protection cap is poured to the side, awayfrom the columnar pile body, of the isolating layer. The problems that in the correlation technique, when the single-pile foundation is subjected to secondary pouring, the construction period is long, and the quality of the single-pile foundation during secondary pouring is hard to guarantee are solved, and the effects of shortening the construction period and guaranteeing the quality of the single-pile foundation are achieved.
本申请公开了一种用于输电线路的单桩基础以及单桩基础制造方法,属于单桩基础制造领域。单桩基础包括:多个连接纵筋以及具有至少四个柱状预埋件的柱状桩体,多个连接纵筋位于至少四个柱状预埋件在目标端面外的部分的四周,多个连接纵筋具有绑扎结构;柱状桩体的目标端面具有隔离层,至少四个柱状预埋件均穿过隔离层;至少四个柱状预埋件位于目标端面外的一端上具有保护套;多个连接纵筋上具有第一金属网片;在隔离层远离柱状桩体的一侧浇筑有混凝土保护帽。解决了相关技术中对单桩基础进行二次浇筑时,施工周期较长,且难以保证二次浇筑时单桩基础的质量的问题。达到了减小施工周期,保证单桩基础质量的效果。
Single-pile foundation for electric transmission line and method for manufacturing single-pile foundation
The invention discloses a single-pile foundation for an electric transmission line and a method for manufacturing the single-pile foundation, and belongs to the field of single-pile foundation manufacturing. The single-pile foundation comprises multiple connecting longitudinal ribs and a columnar pile body with at least four columnar embedded parts. The multiple connecting longitudinal ribs are located around the portions, outside a target end face, of the at least four columnar embedded parts. The multiple connecting longitudinal ribs are provided with binding structures. The target end faceof the columnar pile body is provided with an isolating layer, and the at least four columnar embedded parts penetrate through the isolating layer. Protection sleeves are arranged at the ends, on thetarget end face, of the at least four columnar embedded parts. The multiple connecting longitudinal ribs are provided with first metal net sheets. A concrete protection cap is poured to the side, awayfrom the columnar pile body, of the isolating layer. The problems that in the correlation technique, when the single-pile foundation is subjected to secondary pouring, the construction period is long, and the quality of the single-pile foundation during secondary pouring is hard to guarantee are solved, and the effects of shortening the construction period and guaranteeing the quality of the single-pile foundation are achieved.
本申请公开了一种用于输电线路的单桩基础以及单桩基础制造方法,属于单桩基础制造领域。单桩基础包括:多个连接纵筋以及具有至少四个柱状预埋件的柱状桩体,多个连接纵筋位于至少四个柱状预埋件在目标端面外的部分的四周,多个连接纵筋具有绑扎结构;柱状桩体的目标端面具有隔离层,至少四个柱状预埋件均穿过隔离层;至少四个柱状预埋件位于目标端面外的一端上具有保护套;多个连接纵筋上具有第一金属网片;在隔离层远离柱状桩体的一侧浇筑有混凝土保护帽。解决了相关技术中对单桩基础进行二次浇筑时,施工周期较长,且难以保证二次浇筑时单桩基础的质量的问题。达到了减小施工周期,保证单桩基础质量的效果。
Single-pile foundation for electric transmission line and method for manufacturing single-pile foundation
用于输电线路的单桩基础以及单桩基础制造方法
WANG ZHIFEI (Autor:in) / ZHANG PEISHI (Autor:in) / YIN YASHENG (Autor:in)
21.04.2020
Patent
Elektronische Ressource
Chinesisch
Single-pile foundation and single-pile foundation manufacturing method
Europäisches Patentamt | 2020
|