Construction process of special-shaped transparent aluminum veneer ceiling under steel truss
The invention discloses a construction process of a special-shaped transparent aluminum veneer ceiling under a steel truss. The process comprises the following steps of firstly, joint checking of a drawing and secondary design; secondly, design scheme disclosure; thirdly, suspender and keel machining and mounting; and fourthly, aluminum veneer mounting construction. Due to the application, a one-time molding good rate of construction of the special-shaped transparent aluminum veneer ceiling under the steel truss can be improved, rigidity and safety stability of the ceiling are greatly improved, a large amount of ceiling maintenance and repair construction can be avoided, the ceiling decoration construction duration can be shortened, input of persons and materials can be reduced, and through diversification and visualization disclosure of the BIM technology, animation demonstration, VR and the like, the good condition is created for subsequent decoration and construction.
本发明公开了一种钢桁架下异形透空铝单板吊顶施工工艺,包括下列步骤:(一)图纸会审及二次设计;(二)设计方案交底;(三)吊杆、龙骨加工及安装;(四)铝单板安装施工。本发明的应用,不仅提高了钢桁架下异形透空铝单板吊顶施工一次成型优良率,也大大提高了吊顶结构的刚性和安全稳定性,避免了大量吊顶维修、返修施工,缩短了吊顶装饰施工工期,减少了人员材料的投入;通过BIM技术、动画演示、VR等多元化、可视化的交底,为后续装修施工创造了良好的条件。
Construction process of special-shaped transparent aluminum veneer ceiling under steel truss
The invention discloses a construction process of a special-shaped transparent aluminum veneer ceiling under a steel truss. The process comprises the following steps of firstly, joint checking of a drawing and secondary design; secondly, design scheme disclosure; thirdly, suspender and keel machining and mounting; and fourthly, aluminum veneer mounting construction. Due to the application, a one-time molding good rate of construction of the special-shaped transparent aluminum veneer ceiling under the steel truss can be improved, rigidity and safety stability of the ceiling are greatly improved, a large amount of ceiling maintenance and repair construction can be avoided, the ceiling decoration construction duration can be shortened, input of persons and materials can be reduced, and through diversification and visualization disclosure of the BIM technology, animation demonstration, VR and the like, the good condition is created for subsequent decoration and construction.
本发明公开了一种钢桁架下异形透空铝单板吊顶施工工艺,包括下列步骤:(一)图纸会审及二次设计;(二)设计方案交底;(三)吊杆、龙骨加工及安装;(四)铝单板安装施工。本发明的应用,不仅提高了钢桁架下异形透空铝单板吊顶施工一次成型优良率,也大大提高了吊顶结构的刚性和安全稳定性,避免了大量吊顶维修、返修施工,缩短了吊顶装饰施工工期,减少了人员材料的投入;通过BIM技术、动画演示、VR等多元化、可视化的交底,为后续装修施工创造了良好的条件。
Construction process of special-shaped transparent aluminum veneer ceiling under steel truss
钢桁架下异形透空铝单板吊顶施工工艺
ZHANG SHEN (Autor:in) / ZHENG JIANGUO (Autor:in) / SHANG BAOYING (Autor:in) / GAO GUOLIANG (Autor:in)
24.04.2020
Patent
Elektronische Ressource
Chinesisch
Aluminum veneer suspended ceiling construction process
Europäisches Patentamt | 2020
|Construction method of steel joist of special-shaped aluminum veneer system
Europäisches Patentamt | 2024
|Detachable suspended ceiling decorative aluminum veneer
Europäisches Patentamt | 2023
|Deformation control construction process for multi-curved-surface special-shaped aluminum veneer
Europäisches Patentamt | 2024
|