Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Underground continuous wall construction method aiming at underground loose soil layer
The invention discloses an underground continuous wall construction method aiming at an underground loose soil layer, and belongs to the field of construction engineering. A reinforcement cage of an underground continuous wall structure is included and comprises a fixing structure, a loose soil layer formwork is fixed to the reinforcement cage through the fixing structure, the fixing structure comprises reinforcements and fixed joints, and formwork fixing screws are fixedly connected to the fixed joints. When an underground continuous wall groove section is poured, the method is used so that it can be ensured that concrete at the hole collapse position of a pebble layer does not leak a lot, the flatness quality of the underground continuous wall section is good during later excavation, a lot of manpower and material resources do not need to be consumed to carry out concrete breaking work, mounting is convenient in a construction technology, and practicability is high.
本发明公开了一种针对地下存在松散土层的地下连续墙施工方法,属于建筑工程领域,包括地下连续墙结构的钢筋笼,包括固定结构,所述钢筋笼通过固定结构固定有松散土层模板,所述固定结构包括钢筋和固定节点,所述固定节点处固定连接模板固定螺杆。本发明在地下连续墙槽段浇筑时使用本工法可以保证卵石层塌孔位置砼不会大量渗漏,后期开挖时该段地下连续墙平整度的质量较好,也不必耗费大量人力物力来进行混凝土破除工作,且施工工艺安装方便,具有较强的实用性。
Underground continuous wall construction method aiming at underground loose soil layer
The invention discloses an underground continuous wall construction method aiming at an underground loose soil layer, and belongs to the field of construction engineering. A reinforcement cage of an underground continuous wall structure is included and comprises a fixing structure, a loose soil layer formwork is fixed to the reinforcement cage through the fixing structure, the fixing structure comprises reinforcements and fixed joints, and formwork fixing screws are fixedly connected to the fixed joints. When an underground continuous wall groove section is poured, the method is used so that it can be ensured that concrete at the hole collapse position of a pebble layer does not leak a lot, the flatness quality of the underground continuous wall section is good during later excavation, a lot of manpower and material resources do not need to be consumed to carry out concrete breaking work, mounting is convenient in a construction technology, and practicability is high.
本发明公开了一种针对地下存在松散土层的地下连续墙施工方法,属于建筑工程领域,包括地下连续墙结构的钢筋笼,包括固定结构,所述钢筋笼通过固定结构固定有松散土层模板,所述固定结构包括钢筋和固定节点,所述固定节点处固定连接模板固定螺杆。本发明在地下连续墙槽段浇筑时使用本工法可以保证卵石层塌孔位置砼不会大量渗漏,后期开挖时该段地下连续墙平整度的质量较好,也不必耗费大量人力物力来进行混凝土破除工作,且施工工艺安装方便,具有较强的实用性。
Underground continuous wall construction method aiming at underground loose soil layer
一种针对地下存在松散土层的地下连续墙施工方法
CHEN FEI (Autor:in) / XING YUEDONG (Autor:in) / RUAN FAN (Autor:in)
05.06.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
CONSTRUCTION METHOD OF UNDERGROUND CONTINUOUS WALL AND UNDERGROUND CONTINUOUS WALL
Europäisches Patentamt | 2017
|CONSTRUCTION METHOD OF UNDERGROUND CONTINUOUS WALL, AND UNDERGROUND CONTINUOUS WALL
Europäisches Patentamt | 2017
|CONTINUOUS UNDERGROUND WALL, AND CONSTRUCTION METHOD OF CONTINUOUS UNDERGROUND WALL
Europäisches Patentamt | 2020
|SOIL CEMENT UNDERGROUND CONTINUOUS WALL CONSTRUCTION METHOD
Europäisches Patentamt | 2021
|UNDERGROUND CONTINUOUS WALL AND CONSTRUCTION METHOD FOR UNDERGROUND CONTINUOUS WALL
Europäisches Patentamt | 2020
|