Steel structure elevator shaft inner wall fireproof plugging process
The invention discloses a steel structure elevator shaft inner wall fireproof plugging process. The process comprises the following steps: S1: in the process of construction, after building an integrated floor slab and completing connection and fixing, anti-corrosion process treatment is conducted; S2: an elevator shaft is assembled and welded from steel structure prefabricated components in a factory workshop, and assembly forming of a finished elevator shaft is completed; and S3: dual-layered fiber reinforcing calcium silicate boards are used to fixed the inner periphery of a well of the elevator shaft, the dual-layered fiber reinforcing calcium silicate boards are 12mm in thickness, and the dual-layered fiber reinforcing calcium silicate boards are punched and fixedly installed on the steel structure elevator shaft by expansion screws. A safe and high-efficiency floor layer plugging method of the steel structure assembled elevator shaft is provided, the 12mm-thick dual-layered fiberreinforcing calcium silicate boards are used to duly fixed the periphery of a finished steel floor layer elevator shaft in the factory workshop, the difficulty of onsite construction is reduced, thestability is guaranteed, the elevator construction period is shortened, and safety of construction personnel is ensured.
本发明公开了一种钢结构电梯井内壁防火封堵工艺,包括如下步骤,S1:在建筑施工中对集成楼盖完成搭建以及衔接固定结束后对其进行防腐工艺处理,S2:在工厂车间通过钢结构预制配件组建并焊接电梯井,完成成品电梯井的搭建成型,S3:对成品电梯井井道内部四周采用双层纤维增强硅酸钙板进行固定,双层纤维增强硅酸钙板厚度为12mm,双层纤维增强硅酸钙板与钢结构电梯井之间通过膨胀螺丝打孔安装固定,本发明的目的在于提供提供一种钢结构装配式建筑电梯井安全及高效的楼板层封堵方式,采用双层12mm纤维增强硅酸钙板在车间对做好的钢楼层板电梯井四周进行固定,减少了现场施工的施工难度,保证了稳定性缩短了电梯施工工期,确保了施工人员的安全性。
Steel structure elevator shaft inner wall fireproof plugging process
The invention discloses a steel structure elevator shaft inner wall fireproof plugging process. The process comprises the following steps: S1: in the process of construction, after building an integrated floor slab and completing connection and fixing, anti-corrosion process treatment is conducted; S2: an elevator shaft is assembled and welded from steel structure prefabricated components in a factory workshop, and assembly forming of a finished elevator shaft is completed; and S3: dual-layered fiber reinforcing calcium silicate boards are used to fixed the inner periphery of a well of the elevator shaft, the dual-layered fiber reinforcing calcium silicate boards are 12mm in thickness, and the dual-layered fiber reinforcing calcium silicate boards are punched and fixedly installed on the steel structure elevator shaft by expansion screws. A safe and high-efficiency floor layer plugging method of the steel structure assembled elevator shaft is provided, the 12mm-thick dual-layered fiberreinforcing calcium silicate boards are used to duly fixed the periphery of a finished steel floor layer elevator shaft in the factory workshop, the difficulty of onsite construction is reduced, thestability is guaranteed, the elevator construction period is shortened, and safety of construction personnel is ensured.
本发明公开了一种钢结构电梯井内壁防火封堵工艺,包括如下步骤,S1:在建筑施工中对集成楼盖完成搭建以及衔接固定结束后对其进行防腐工艺处理,S2:在工厂车间通过钢结构预制配件组建并焊接电梯井,完成成品电梯井的搭建成型,S3:对成品电梯井井道内部四周采用双层纤维增强硅酸钙板进行固定,双层纤维增强硅酸钙板厚度为12mm,双层纤维增强硅酸钙板与钢结构电梯井之间通过膨胀螺丝打孔安装固定,本发明的目的在于提供提供一种钢结构装配式建筑电梯井安全及高效的楼板层封堵方式,采用双层12mm纤维增强硅酸钙板在车间对做好的钢楼层板电梯井四周进行固定,减少了现场施工的施工难度,保证了稳定性缩短了电梯施工工期,确保了施工人员的安全性。
Steel structure elevator shaft inner wall fireproof plugging process
一种钢结构电梯井内壁防火封堵工艺
WANG JING (Autor:in) / SUN WEI (Autor:in) / XIAO CHANGGENG (Autor:in) / WU SIYANG (Autor:in)
11.08.2020
Patent
Elektronische Ressource
Chinesisch
Novel steel structure curtain wall interlayer fireproof plugging system structure
Europäisches Patentamt | 2024
|Fireproof plugging structure at joint of partition wall and roof
Europäisches Patentamt | 2024
|