The invention belongs to the technical field of pipe gallery mold plate trolley construction, and especially relates to a construction technology for an outdoor comprehensive pipe gallery mold plate trolley. The construction technology comprises the following steps of: transporting a steel mold trolley to a site after completing the processing of the steel mold trolley in a factory, and installingthe steel mold trolley on the site by adopting a 25t truck-mounted crane in cooperation with manual work, wherein the installing sequence is as follows: walking system-main truss of the trolley-spiral screw rod-hydraulic system-inner side steel mold plate-top plate steel mold plate-clamp device. The steel mold trolley is used for the construction of a pipe gallery structure; the steel mold trolley construction has higher degree of mechanization than the traditional wooden mold construction; only a few trolley operators are needed on the site; the number of operators for erecting mold plates on the site is minimized; and compared with the wooden mold and steel mold construction, the steel mold trolley construction has the advantages that the material expenses of the mold plates, and the cost of labor and mechanical equipment are relatively low; the mold plate erecting time is short; the construction period is saved; the molding quality of concrete is relatively good; the construction period is shortened; the cost is saved; and good quality effects have been achieved.
本发明属于管廊模板台车施工技术领域,尤其为室外综合管廊模板台车施工工艺,包括如下步骤,钢模台车在工厂加工完成后,运至现场,采用25t汽车吊和人工配合进行现场安装;安装顺序为:行走系统‑台车主桁架‑螺旋丝杆‑液压系统‑内侧钢模板‑顶板钢模板‑紧固装置;本发明采用钢模台车进行管廊结构施工,钢模台车施工较传统木模施工机械化程度高,现场只有少数台车操作工人,极少减少现场模板支设劳务作业人员数量,钢模台车施工相较木模和钢模施工,模板材料费、人工费、机械设备费相对较低,且支模时间短,节约工期,混凝土成型质量较好,缩短了工期,节约了成本,并取得了良好的质量效果。
The invention belongs to the technical field of pipe gallery mold plate trolley construction, and especially relates to a construction technology for an outdoor comprehensive pipe gallery mold plate trolley. The construction technology comprises the following steps of: transporting a steel mold trolley to a site after completing the processing of the steel mold trolley in a factory, and installingthe steel mold trolley on the site by adopting a 25t truck-mounted crane in cooperation with manual work, wherein the installing sequence is as follows: walking system-main truss of the trolley-spiral screw rod-hydraulic system-inner side steel mold plate-top plate steel mold plate-clamp device. The steel mold trolley is used for the construction of a pipe gallery structure; the steel mold trolley construction has higher degree of mechanization than the traditional wooden mold construction; only a few trolley operators are needed on the site; the number of operators for erecting mold plates on the site is minimized; and compared with the wooden mold and steel mold construction, the steel mold trolley construction has the advantages that the material expenses of the mold plates, and the cost of labor and mechanical equipment are relatively low; the mold plate erecting time is short; the construction period is saved; the molding quality of concrete is relatively good; the construction period is shortened; the cost is saved; and good quality effects have been achieved.
本发明属于管廊模板台车施工技术领域,尤其为室外综合管廊模板台车施工工艺,包括如下步骤,钢模台车在工厂加工完成后,运至现场,采用25t汽车吊和人工配合进行现场安装;安装顺序为:行走系统‑台车主桁架‑螺旋丝杆‑液压系统‑内侧钢模板‑顶板钢模板‑紧固装置;本发明采用钢模台车进行管廊结构施工,钢模台车施工较传统木模施工机械化程度高,现场只有少数台车操作工人,极少减少现场模板支设劳务作业人员数量,钢模台车施工相较木模和钢模施工,模板材料费、人工费、机械设备费相对较低,且支模时间短,节约工期,混凝土成型质量较好,缩短了工期,节约了成本,并取得了良好的质量效果。
Construction technology for outdoor comprehensive pipe gallery mold plate trolley
室外综合管廊模板台车施工工艺
28.08.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Universal comprehensive pipe gallery construction trolley
Europäisches Patentamt | 2023
|Comprehensive pipe gallery hydraulic formwork trolley and construction method
Europäisches Patentamt | 2023
|Municipal comprehensive pipe gallery hydraulic trolley
Europäisches Patentamt | 2021
|Rectangular trolley for comprehensive pipe gallery and construction method
Europäisches Patentamt | 2020
|