Construction method of cast-in-place beam movable formwork
The invention discloses a construction method of cast-in-place beam movable formwork, which comprises the steps of A, building a temporary support, and cleaning the temporary support; B, mounting a pier-side bracket; C, mounting a supporting trolley; D, erecting a steel box girder; E, mounting a bottom template; F, mounting an outer side mold; G, mounting a balance weight and a platform; H, mounting an internal mold system and top plate reinforcing steel bars; I, mounting an end die; and J, mounting other accessories. The construction method of the cast-in-place beam movable formwork is simplein step; the construction efficiency can be effectively improved in the implementation process; the construction method of the cast-in-place beam movable formwork is safe and reliable, the construction method is designed into a set of fixed program, and the replicable rate is high; and compared with other methods, the construction method has remarkable advantages, the construction progress is greatly accelerated, the construction cost is saved, and a great promotion effect is achieved in the bridge construction field of China.
本发明公开了一种现浇梁移动模架施工方法,该包括以下步骤:该现浇梁移动模架施工方法包括以下步骤:A、搭建临时支架,对临时支架进行清理;B、安装墩旁托架;C、安装支撑台车;D、架设钢箱梁;E、安装底模板;F、安装外侧模;G、安装配重及平台;H、安装内模系统及顶板钢筋;I、安装端模;J、其他附件的安装;本发明的现浇梁移动模架施工方法步骤简单,实施过程中能够有效的提高施工效率,并且该现浇梁移动模架施工方法安全可靠,将施工方法设计成一套固定程序,可复制率高,较其他的方法比较有着显著优势,不仅大大加快了施工进度还节约了施工成本,对我国的桥梁施工领域都起着极大的促进作用。
Construction method of cast-in-place beam movable formwork
The invention discloses a construction method of cast-in-place beam movable formwork, which comprises the steps of A, building a temporary support, and cleaning the temporary support; B, mounting a pier-side bracket; C, mounting a supporting trolley; D, erecting a steel box girder; E, mounting a bottom template; F, mounting an outer side mold; G, mounting a balance weight and a platform; H, mounting an internal mold system and top plate reinforcing steel bars; I, mounting an end die; and J, mounting other accessories. The construction method of the cast-in-place beam movable formwork is simplein step; the construction efficiency can be effectively improved in the implementation process; the construction method of the cast-in-place beam movable formwork is safe and reliable, the construction method is designed into a set of fixed program, and the replicable rate is high; and compared with other methods, the construction method has remarkable advantages, the construction progress is greatly accelerated, the construction cost is saved, and a great promotion effect is achieved in the bridge construction field of China.
本发明公开了一种现浇梁移动模架施工方法,该包括以下步骤:该现浇梁移动模架施工方法包括以下步骤:A、搭建临时支架,对临时支架进行清理;B、安装墩旁托架;C、安装支撑台车;D、架设钢箱梁;E、安装底模板;F、安装外侧模;G、安装配重及平台;H、安装内模系统及顶板钢筋;I、安装端模;J、其他附件的安装;本发明的现浇梁移动模架施工方法步骤简单,实施过程中能够有效的提高施工效率,并且该现浇梁移动模架施工方法安全可靠,将施工方法设计成一套固定程序,可复制率高,较其他的方法比较有着显著优势,不仅大大加快了施工进度还节约了施工成本,对我国的桥梁施工领域都起着极大的促进作用。
Construction method of cast-in-place beam movable formwork
一种现浇梁移动模架施工方法
ZOU CHUNJUN (Autor:in)
04.09.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Movable formwork cast-in-place aqueduct construction method
Europäisches Patentamt | 2024
|Movable formwork cast-in-place beam steam curing device
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2024
|Movable formwork cast-in-place beam end sealing adjustable formwork and end sealing method
Europäisches Patentamt | 2024
|Movable formwork cast-in-place beam maintenance method and maintenance system
Europäisches Patentamt | 2021
|