Fabricated pier and construction process thereof
The invention discloses a fabricated pier and a construction process thereof. The assembly type pier comprises a plurality of tubular piles, a bearing platform, a pier column and a cover beam. The tubular piles are arranged at the lower end of the bearing platform and connected with the bearing platform, the lower ends of the piers are mounted in pier positioning grooves in the upper end surface of the bearing platform, and the upper end and the cover beam are connected, prefabricated assembly is adopted in the construction process, all parts of the fabricated pier are prefabricated, and spliced, installed and constructed in parallel after being prefabricated, the construction period is greatly shortened, the influence of construction on the surrounding environment is improved, the appearance quality and the entity quality of engineering are improved, and the fabricated pier has the advantages of being high in standardization degree in the construction process, good in cost control effect and high in construction quality.
本发明公开了一种装配式桥墩及其施工工艺,装配式桥墩包括多根管桩、承台、墩柱和盖梁,管桩设置在承台的下端,与承台连接,墩柱的下端安装在承台上端面的墩柱定位槽中,上端与盖梁连接,其施工工艺采用预制拼装,将装配式桥墩的各个部分进行预制,并在预制后进行拼接安装,平行施工,极大的节省了工期、改善了施工对周边环境的影响、提高了工程的外观质量和实体质量,具有施工过程标准化程度高、成本控制效果好、施工质量高的特点。
Fabricated pier and construction process thereof
The invention discloses a fabricated pier and a construction process thereof. The assembly type pier comprises a plurality of tubular piles, a bearing platform, a pier column and a cover beam. The tubular piles are arranged at the lower end of the bearing platform and connected with the bearing platform, the lower ends of the piers are mounted in pier positioning grooves in the upper end surface of the bearing platform, and the upper end and the cover beam are connected, prefabricated assembly is adopted in the construction process, all parts of the fabricated pier are prefabricated, and spliced, installed and constructed in parallel after being prefabricated, the construction period is greatly shortened, the influence of construction on the surrounding environment is improved, the appearance quality and the entity quality of engineering are improved, and the fabricated pier has the advantages of being high in standardization degree in the construction process, good in cost control effect and high in construction quality.
本发明公开了一种装配式桥墩及其施工工艺,装配式桥墩包括多根管桩、承台、墩柱和盖梁,管桩设置在承台的下端,与承台连接,墩柱的下端安装在承台上端面的墩柱定位槽中,上端与盖梁连接,其施工工艺采用预制拼装,将装配式桥墩的各个部分进行预制,并在预制后进行拼接安装,平行施工,极大的节省了工期、改善了施工对周边环境的影响、提高了工程的外观质量和实体质量,具有施工过程标准化程度高、成本控制效果好、施工质量高的特点。
Fabricated pier and construction process thereof
一种装配式桥墩及其施工工艺
YUAN PINGLI (Autor:in) / JIAO GUANGYAN (Autor:in) / WANG WEITAO (Autor:in) / ZHANG TIEFENG (Autor:in) / LU PENGHUI (Autor:in) / YAN XIAOLONG (Autor:in) / WANG BO (Autor:in)
11.09.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
/
B28B
Formgeben von Ton oder anderen keramischen Stoffzusammensetzungen, Schlacke oder von Mischungen, die zementartiges Material enthalten, z.B. Putzmörtel
,
SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
/
E02D
FOUNDATIONS
,
Gründungen
Fabricated pier column structure and construction method thereof
Europäisches Patentamt | 2023
|Fabricated concrete pier connecting structure and construction method thereof
Europäisches Patentamt | 2022
|