Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Fill slope anchor pile retaining wall structure and construction method thereof
The invention relates to the technical field of slope support, in particular to a construction method of a fill slope anchor pile retaining wall structure. The construction method comprises the following steps that slide-resistant piles and first-order inter-pile baffles are constructed; first-time filling soil is conducted; a first row of anchor cables are constructed, and tensioning is conductedafter the anchorage sections of the anchor cables reach the designed strength; second-order inter-pile baffles and second-time filling soil are constructed; a second row of anchor cables are constructed, tensioning is conducted after the anchorage sections of the anchor cables reach the designed strength, and the nth step, the nth inter-pile baffles and the nth filling are constructed in sequence; and nth, the nth row of anchor cables are constructed, tensioning is conducted after the anchorage sections of the anchor cables reach the designed strength, and construction of the n rows of anchorcables on the slide-resistant piles is completed in sequence. The method has the beneficial effects that the defect that a traditional anchor pile retaining wall cannot be used for filling a side slope is overcome, the multiple rows of anchor cables are arranged on the piles through top-down reverse construction, the construction method is simple, constraint is provided through the multiple rowsof anchor cables, and the reliability and economical efficiency of a supporting structure are improved.
本发明涉及边坡支护技术领域,尤其涉及一种填方边坡锚拉桩挡墙结构的施工方法,施工方法包括:施工抗滑桩和第一阶桩间挡板;第一次填土;施工第一排锚索,待锚索锚固段达到设计强度后进行张拉;施工第二阶桩间挡板与第二次填土;施工第二排锚索,待锚索锚固段达到设计强度后进行张拉,依次,第n‑1步、施工第n阶桩间挡板与第n次填土;第n步、施工第n排锚索,待锚索锚固段达到设计强度后进行张拉,依次完成抗滑桩上n排锚索的施工。本发明的有益效果是:改变了传统的锚拉桩挡墙不能用于填方边坡的弊端,通过自下而上的逆作法施工,在桩上设置多排锚索,施工方法简单,通过多排锚索提供约束,提高了支护结构的可靠性和经济性。
Fill slope anchor pile retaining wall structure and construction method thereof
The invention relates to the technical field of slope support, in particular to a construction method of a fill slope anchor pile retaining wall structure. The construction method comprises the following steps that slide-resistant piles and first-order inter-pile baffles are constructed; first-time filling soil is conducted; a first row of anchor cables are constructed, and tensioning is conductedafter the anchorage sections of the anchor cables reach the designed strength; second-order inter-pile baffles and second-time filling soil are constructed; a second row of anchor cables are constructed, tensioning is conducted after the anchorage sections of the anchor cables reach the designed strength, and the nth step, the nth inter-pile baffles and the nth filling are constructed in sequence; and nth, the nth row of anchor cables are constructed, tensioning is conducted after the anchorage sections of the anchor cables reach the designed strength, and construction of the n rows of anchorcables on the slide-resistant piles is completed in sequence. The method has the beneficial effects that the defect that a traditional anchor pile retaining wall cannot be used for filling a side slope is overcome, the multiple rows of anchor cables are arranged on the piles through top-down reverse construction, the construction method is simple, constraint is provided through the multiple rowsof anchor cables, and the reliability and economical efficiency of a supporting structure are improved.
本发明涉及边坡支护技术领域,尤其涉及一种填方边坡锚拉桩挡墙结构的施工方法,施工方法包括:施工抗滑桩和第一阶桩间挡板;第一次填土;施工第一排锚索,待锚索锚固段达到设计强度后进行张拉;施工第二阶桩间挡板与第二次填土;施工第二排锚索,待锚索锚固段达到设计强度后进行张拉,依次,第n‑1步、施工第n阶桩间挡板与第n次填土;第n步、施工第n排锚索,待锚索锚固段达到设计强度后进行张拉,依次完成抗滑桩上n排锚索的施工。本发明的有益效果是:改变了传统的锚拉桩挡墙不能用于填方边坡的弊端,通过自下而上的逆作法施工,在桩上设置多排锚索,施工方法简单,通过多排锚索提供约束,提高了支护结构的可靠性和经济性。
Fill slope anchor pile retaining wall structure and construction method thereof
一种填方边坡锚拉桩挡墙结构以及施工方法
GAN FEI (Autor:in) / LI MEILIN (Autor:in) / ZHAO YU (Autor:in) / ZHANG YI (Autor:in) / MENG BAOHUA (Autor:in) / BI JING (Autor:in) / WANG CHAOLIN (Autor:in) / YANG JUN (Autor:in) / YE XIAOMING (Autor:in) / YIN KE (Autor:in)
18.09.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Retaining structure of fill slope and construction method thereof
Europäisches Patentamt | 2020
|Anchor pile type gravity retaining wall and construction method thereof
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Anchor cable slide-resistant pile side slope retaining structure
Europäisches Patentamt | 2024
|Slope prestressed pile-wall-anchor composite support structure and construction method
Europäisches Patentamt | 2021
|