Constructional pillar top construction method using precast triangular concrete blocks as oblique crown bricks
The invention provides a constructional pillar top construction method using precast triangular concrete blocks as oblique crown bricks. The method is characterized by comprising the following steps that 1, the height between the lower surface of a structural beam or plate and the surface of the top end of constructional pillar filling wall brick masonries is measured; 2, a plurality of triangularconcrete blocks are precast according to the measured height; 3, a plurality of bricks are provided, so that the bricks are obliquely laid between the lower surface of the structural beam or plate and the surface of the top end of the constructional pillar filling wall brick masonries; 4, a wooden formwork and a wooden square supporting formwork are adopted at the top of a constructional pillar;and 5, after operation of the constructional pillar concrete formwork is completed, concrete is poured, and the constructional pillar top construction using the precast triangular concrete blocks as the oblique crown bricks is completed. The constructional pillar top construction method using the precast triangular concrete blocks as the oblique crown bricks has the advantages that the precast triangular concrete blocks are simple in structure and convenient to manufacture, an upper opening of a constructional pillar can be well blocked, it is guaranteed that the oblique crown bricks are compact in packing, the constructional pillar forming and the qualities of the brick masonries and the constructional pillar are good, the constructional pillar supporting formwork is conveniently constructed, the construction speed is increased, and the engineering cost is reduced.
一种用预制三角砼块作斜顶砖的构造柱顶部施工方法,其特征在于包括以下步骤:a、量出结构梁或板下表面与构造柱填充墙砖砌体顶端表面之间的高度,b、根据测量出的所述高度预制若干三角砼块,c、提供若干砖块,使砖块在构梁或板下表面与构造柱填充墙砖砌体顶端表面之间斜砌,d、在构造柱顶部采用木模板和木方支模,e、构造柱混凝土模板作业完成后,浇筑混凝土,完成用预制三角砼块作斜顶砖的构造柱顶部施工。本发明的用预制三角砼块作斜顶砖的构造柱顶部施工方法具有预制三角砼块结构简单、制作方便,能很好的封堵构造柱上口,保证斜顶砖填塞密实,构造柱成型、砖砌体及构造柱质量较好,方便构造柱支模,提高施工速度和降低工程成本的优点。
Constructional pillar top construction method using precast triangular concrete blocks as oblique crown bricks
The invention provides a constructional pillar top construction method using precast triangular concrete blocks as oblique crown bricks. The method is characterized by comprising the following steps that 1, the height between the lower surface of a structural beam or plate and the surface of the top end of constructional pillar filling wall brick masonries is measured; 2, a plurality of triangularconcrete blocks are precast according to the measured height; 3, a plurality of bricks are provided, so that the bricks are obliquely laid between the lower surface of the structural beam or plate and the surface of the top end of the constructional pillar filling wall brick masonries; 4, a wooden formwork and a wooden square supporting formwork are adopted at the top of a constructional pillar;and 5, after operation of the constructional pillar concrete formwork is completed, concrete is poured, and the constructional pillar top construction using the precast triangular concrete blocks as the oblique crown bricks is completed. The constructional pillar top construction method using the precast triangular concrete blocks as the oblique crown bricks has the advantages that the precast triangular concrete blocks are simple in structure and convenient to manufacture, an upper opening of a constructional pillar can be well blocked, it is guaranteed that the oblique crown bricks are compact in packing, the constructional pillar forming and the qualities of the brick masonries and the constructional pillar are good, the constructional pillar supporting formwork is conveniently constructed, the construction speed is increased, and the engineering cost is reduced.
一种用预制三角砼块作斜顶砖的构造柱顶部施工方法,其特征在于包括以下步骤:a、量出结构梁或板下表面与构造柱填充墙砖砌体顶端表面之间的高度,b、根据测量出的所述高度预制若干三角砼块,c、提供若干砖块,使砖块在构梁或板下表面与构造柱填充墙砖砌体顶端表面之间斜砌,d、在构造柱顶部采用木模板和木方支模,e、构造柱混凝土模板作业完成后,浇筑混凝土,完成用预制三角砼块作斜顶砖的构造柱顶部施工。本发明的用预制三角砼块作斜顶砖的构造柱顶部施工方法具有预制三角砼块结构简单、制作方便,能很好的封堵构造柱上口,保证斜顶砖填塞密实,构造柱成型、砖砌体及构造柱质量较好,方便构造柱支模,提高施工速度和降低工程成本的优点。
Constructional pillar top construction method using precast triangular concrete blocks as oblique crown bricks
一种用预制三角砼块作斜顶砖的构造柱顶部施工方法
JIANG HUAJING (Autor:in) / LI MING (Autor:in) / LU YUHONG (Autor:in) / ZHAO DEXIN (Autor:in) / YANG TAO (Autor:in)
02.10.2020
Patent
Elektronische Ressource
Chinesisch
CONSTRUCTION METHOD OF PILLAR/BEAM USING PRECAST CONCRETE PILLAR
Europäisches Patentamt | 2017
|Precast concrete hollow blocks
Engineering Index Backfile | 1940
Europäisches Patentamt | 2021
|PRECAST CONCRETE STRUCTURE AND PRECAST CONCRETE CONSTRUCTION METHOD
Europäisches Patentamt | 2022
|