Cantilever type double-argil-plate curtain wall dry hanging construction method based on BIM technology
The invention discloses a cantilever type double-argil-plate curtain wall dry hanging construction method based on the BIM technology. The method comprises the following specific construction steps: 1, creating a curtain wall model: according to a building construction design drawing, creating a curtain wall model by adopting an Rhino + Grasshopper plug-in, inputting a curtain wall three-dimensional drawing into Revit, creating a curtain wall entity model through Revit software, and inputting physical and functional information; 2, simulating the construction progress: associating the information model with the construction progress information through Navisworks software to form simulation of the construction progress of the model + time dimension, and arranging construction steps and a construction organization scheme through the construction progress; 3, analyzing soft collision occurring in a curtain wall construction link by utilizing the BIM, and deepening and adjusting a construction scheme; 4, guiding construction through a BIM model in the construction process; by applying the BIM technology, risk control over the technology, management and project operation can be achieved, meanwhile, the problem that curtain wall engineering materials are high in loss is solved, and the project cost is effectively reduced.
本发明公开了一种基于BIM技术的悬臂式双陶土板幕墙干挂施工方法,包括以下具体施工方法:一、幕墙模型创建,根据建筑施工设计图纸,采用Rhino+Grasshopper插件创建幕墙模型,将幕墙三维图纸输入Revit,并通过Revit软件创建幕墙实体模型,并输入物理和功能信息;二、施工进度模拟,通过Navisworks软件,将信息模型同施工进度信息关联,形成模型+时间维度的施工进度的模拟,通过施工进度安排施工步骤和施工组织方案;三、利用BIM模型对幕墙施工环节中出现的软碰撞进行剖析,并对施工方案进行深化和调节;四、施工过程中通过BIM模型指导施工;通过应用BIM技术,可以实现技术、管理和项目经营的风险控制,同时解决了幕墙工程材料损耗高的问题,有效降低了项目成本。
Cantilever type double-argil-plate curtain wall dry hanging construction method based on BIM technology
The invention discloses a cantilever type double-argil-plate curtain wall dry hanging construction method based on the BIM technology. The method comprises the following specific construction steps: 1, creating a curtain wall model: according to a building construction design drawing, creating a curtain wall model by adopting an Rhino + Grasshopper plug-in, inputting a curtain wall three-dimensional drawing into Revit, creating a curtain wall entity model through Revit software, and inputting physical and functional information; 2, simulating the construction progress: associating the information model with the construction progress information through Navisworks software to form simulation of the construction progress of the model + time dimension, and arranging construction steps and a construction organization scheme through the construction progress; 3, analyzing soft collision occurring in a curtain wall construction link by utilizing the BIM, and deepening and adjusting a construction scheme; 4, guiding construction through a BIM model in the construction process; by applying the BIM technology, risk control over the technology, management and project operation can be achieved, meanwhile, the problem that curtain wall engineering materials are high in loss is solved, and the project cost is effectively reduced.
本发明公开了一种基于BIM技术的悬臂式双陶土板幕墙干挂施工方法,包括以下具体施工方法:一、幕墙模型创建,根据建筑施工设计图纸,采用Rhino+Grasshopper插件创建幕墙模型,将幕墙三维图纸输入Revit,并通过Revit软件创建幕墙实体模型,并输入物理和功能信息;二、施工进度模拟,通过Navisworks软件,将信息模型同施工进度信息关联,形成模型+时间维度的施工进度的模拟,通过施工进度安排施工步骤和施工组织方案;三、利用BIM模型对幕墙施工环节中出现的软碰撞进行剖析,并对施工方案进行深化和调节;四、施工过程中通过BIM模型指导施工;通过应用BIM技术,可以实现技术、管理和项目经营的风险控制,同时解决了幕墙工程材料损耗高的问题,有效降低了项目成本。
Cantilever type double-argil-plate curtain wall dry hanging construction method based on BIM technology
一种基于BIM技术的悬臂式双陶土板幕墙干挂施工方法
DENG KANGKANG (Autor:in) / LI WENYUAN (Autor:in) / ZHANG JUANJUAN (Autor:in) / HAO PENGQIAN (Autor:in) / SHI JIANHUA (Autor:in) / HOU YANHONG (Autor:in) / JIA YAFENG (Autor:in)
02.10.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
/
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
Zipper argil plate curtain wall and construction method thereof
Europäisches Patentamt | 2021
|Hanging type long-strip argil brick curtain wall and mounting method thereof
Europäisches Patentamt | 2021
|Argil plate curtain wall structure and construction method thereof
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2024
|