Flow plastic sludge layer drilling wall protection method, pouring method and pouring structure
The invention provides a flow plastic sludge layer drilling wall protection method, a pouring method and a pouring structure, and belongs to the field of building construction. The flow plastic sludgelayer drilling wall protection method comprises the following steps that the position and depth of a flow plastic sludge layer are determined; drilling is conducted; and a protection cylinder is sunkinto a hole and made to penetrate through the flow plastic sludge layer. According to the flow plastic sludge layer drilling wall protection method, the pouring method and the pouring structure, wallprotection is conducted by adopting the method that the protection cylinder penetrates through the flow plastic sludge layer, the working procedure is simple, the construction effect can be improved,accordingly, the construction period is shortened, and the cost is reduced; after wall protection is conducted by adopting the protection cylinder, the poured concrete volume meets the design requirement, and the abnormal phenomena that a waste hole is caused by difficult steel reinforcement cage lowering, and sudden upheaval and the like do not occur to surrounding buildings after hole forming are avoided; and through field pile foundation PDA detection, the detection result shows that a pile body is cylindrical, the pile body is regular, the pile body integrity is excellent, and the pile foundation bearing capacity meets the design and using requirements.
本发明提供一种流塑状淤泥层钻孔护壁方法、钻孔灌注方法和灌注结构,属于建筑施工领域,流塑状淤泥层钻孔护壁方法包括以下步骤:确定流塑状淤泥层的位置和深度;钻孔;向孔内沉入护筒,并使护筒穿过流塑状淤泥层。本发明采用护筒穿过流塑状淤泥层的方法进行护壁,工序简单,能够提高施工效果,进而缩短工期,降低成本;采用护筒护壁后,灌注混凝土方量符合设计要求,成孔后未出现钢筋笼下放困难导致废孔、周围建筑物未出现突然隆起等异常现象,并通过现场桩基PDA检测,检测结果显示桩身形状呈圆柱形,桩身规则,桩身完整性优良,桩基承载力符合设计使用要求。
Flow plastic sludge layer drilling wall protection method, pouring method and pouring structure
The invention provides a flow plastic sludge layer drilling wall protection method, a pouring method and a pouring structure, and belongs to the field of building construction. The flow plastic sludgelayer drilling wall protection method comprises the following steps that the position and depth of a flow plastic sludge layer are determined; drilling is conducted; and a protection cylinder is sunkinto a hole and made to penetrate through the flow plastic sludge layer. According to the flow plastic sludge layer drilling wall protection method, the pouring method and the pouring structure, wallprotection is conducted by adopting the method that the protection cylinder penetrates through the flow plastic sludge layer, the working procedure is simple, the construction effect can be improved,accordingly, the construction period is shortened, and the cost is reduced; after wall protection is conducted by adopting the protection cylinder, the poured concrete volume meets the design requirement, and the abnormal phenomena that a waste hole is caused by difficult steel reinforcement cage lowering, and sudden upheaval and the like do not occur to surrounding buildings after hole forming are avoided; and through field pile foundation PDA detection, the detection result shows that a pile body is cylindrical, the pile body is regular, the pile body integrity is excellent, and the pile foundation bearing capacity meets the design and using requirements.
本发明提供一种流塑状淤泥层钻孔护壁方法、钻孔灌注方法和灌注结构,属于建筑施工领域,流塑状淤泥层钻孔护壁方法包括以下步骤:确定流塑状淤泥层的位置和深度;钻孔;向孔内沉入护筒,并使护筒穿过流塑状淤泥层。本发明采用护筒穿过流塑状淤泥层的方法进行护壁,工序简单,能够提高施工效果,进而缩短工期,降低成本;采用护筒护壁后,灌注混凝土方量符合设计要求,成孔后未出现钢筋笼下放困难导致废孔、周围建筑物未出现突然隆起等异常现象,并通过现场桩基PDA检测,检测结果显示桩身形状呈圆柱形,桩身规则,桩身完整性优良,桩基承载力符合设计使用要求。
Flow plastic sludge layer drilling wall protection method, pouring method and pouring structure
流塑状淤泥层钻孔护壁方法、灌注方法和灌注结构
LIN QIPING (Autor:in) / JIANG XIAOPING (Autor:in) / LI RUIPING (Autor:in) / ZHOU JIANMEI (Autor:in) / XIONG JIANYING (Autor:in) / XIAO GUOZHONG (Autor:in) / YU HANBING (Autor:in) / LI AIPING (Autor:in) / YAO GUANGMING (Autor:in)
13.10.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Plastic flow sludge layer drilling and pouring structure
Europäisches Patentamt | 2023
|Wall column joint concrete pouring structure and pouring method
Europäisches Patentamt | 2024
|Pouring maintenance wall protection template structure
Europäisches Patentamt | 2023
|