Large reserved door opening integrated steel frame slip formwork construction method
The invention relates to a large reserved door opening integrated steel frame slip formwork construction method. The construction method comprises the following steps of S1, designing a drawing, and designing a steel frame according to the size of a door opening; S2, manufacturing the steel frame according to the drawing; S3, hoisting the steel frame; S4, manufacturing and hoisting a slip formworksteel frame; S5, manufacturing a steel vertical formwork; and S6, pouring concrete, pouring concrete of shear walls at the steel vertical formwork and a slip formwork, constructing the slip formwork,assembling the slip formwork steel frame and the steel vertical formwork to form the integrated steel frame slip formwork when the concrete is poured to the elevation of a roof, pouring concrete on the top of the door opening and concrete of the shear walls on the two sides simultaneously, sliding and lifting the slip formwork steel frame and the steel vertical formwork synchronously and conducting construction of the slip formwork. The large reserved door opening integrated steel frame slip formwork construction method has the effects that materials and construction machines can be transported in or out of a site conveniently, and the construction period is shortened.
本申请涉及大型预留门洞一体式钢架滑模施工方法,包括以下步骤,步骤S1:设计图纸,根据门洞的尺寸设计钢架体;步骤S2:根据图纸制作钢架体;步骤S3:吊装钢架体;步骤S4:制作并吊装滑模钢架;步骤S5:制作钢立模;步骤S6:浇筑混凝土,在钢立模与滑模处浇筑剪力墙的混凝土,然后进行滑模施工,当浇筑至洞顶的标高时,将滑模钢架和钢立模拼接,形成一体式钢架滑模,门洞顶部的混凝土与两侧剪力墙的混凝土同时进行浇筑,滑模钢架和钢立模同步滑升进行滑模施工。本申请具有便于材料及施工机器进出场、缩短工期的效果。
Large reserved door opening integrated steel frame slip formwork construction method
The invention relates to a large reserved door opening integrated steel frame slip formwork construction method. The construction method comprises the following steps of S1, designing a drawing, and designing a steel frame according to the size of a door opening; S2, manufacturing the steel frame according to the drawing; S3, hoisting the steel frame; S4, manufacturing and hoisting a slip formworksteel frame; S5, manufacturing a steel vertical formwork; and S6, pouring concrete, pouring concrete of shear walls at the steel vertical formwork and a slip formwork, constructing the slip formwork,assembling the slip formwork steel frame and the steel vertical formwork to form the integrated steel frame slip formwork when the concrete is poured to the elevation of a roof, pouring concrete on the top of the door opening and concrete of the shear walls on the two sides simultaneously, sliding and lifting the slip formwork steel frame and the steel vertical formwork synchronously and conducting construction of the slip formwork. The large reserved door opening integrated steel frame slip formwork construction method has the effects that materials and construction machines can be transported in or out of a site conveniently, and the construction period is shortened.
本申请涉及大型预留门洞一体式钢架滑模施工方法,包括以下步骤,步骤S1:设计图纸,根据门洞的尺寸设计钢架体;步骤S2:根据图纸制作钢架体;步骤S3:吊装钢架体;步骤S4:制作并吊装滑模钢架;步骤S5:制作钢立模;步骤S6:浇筑混凝土,在钢立模与滑模处浇筑剪力墙的混凝土,然后进行滑模施工,当浇筑至洞顶的标高时,将滑模钢架和钢立模拼接,形成一体式钢架滑模,门洞顶部的混凝土与两侧剪力墙的混凝土同时进行浇筑,滑模钢架和钢立模同步滑升进行滑模施工。本申请具有便于材料及施工机器进出场、缩短工期的效果。
Large reserved door opening integrated steel frame slip formwork construction method
大型预留门洞一体式钢架滑模施工方法
LIU ZHE (Autor:in) / DING GUANGCHENG (Autor:in) / WANG XIKUANG (Autor:in) / CAI MINGHONG (Autor:in)
20.10.2020
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Europäisches Patentamt | 2020
|FORMWORK INTEGRATED DOOR FRAME CONSTRUCTION METHOD AND DEVICE
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2022
|Floor pipeline reserved hole plugging formwork and construction method
Europäisches Patentamt | 2021
|Europäisches Patentamt | 2022
|