Trestle-free overwater bridge pile foundation and bearing platform construction method
The invention discloses a trestle-free overwater bridge pile foundation and bearing platform construction method. The construction method adopts a cofferdam and floating bridge combined mode to realize trestle-free construction operation, the cofferdam encloses a construction area in water, and pile foundation and bearing platform construction is carried out in the construction area; the cofferdamis of a rhombus structure, so that water flow impact force borne by the whole cofferdam is smaller, a cofferdam and floating bridge combined mode is adopted to replace a traditional cofferdam and trestle combined mode for construction, and compared with a trestle, the floating bridge is convenient to assemble and disassemble, lower in manufacturing cost and capable of being repeatedly used.
本发明公开了一种无栈桥的水上桥梁桩基及承台施工方法,该施工方法采用围堰和浮桥相结合的方式实现无栈桥的施工作业,所述围堰在水中圈出施工区域,在施工区域的内部进行桩基和承台的施工;本发明中围堰采用菱形结构的方式,使得围堰整体受到的水流冲击力更小,采用围堰加浮桥的方式代替传统的围堰加栈桥的方式进行施工,浮桥相对于栈桥来说,不仅便于进行安装和拆卸,而且造价更低,也能够进行重复的使用。
Trestle-free overwater bridge pile foundation and bearing platform construction method
The invention discloses a trestle-free overwater bridge pile foundation and bearing platform construction method. The construction method adopts a cofferdam and floating bridge combined mode to realize trestle-free construction operation, the cofferdam encloses a construction area in water, and pile foundation and bearing platform construction is carried out in the construction area; the cofferdamis of a rhombus structure, so that water flow impact force borne by the whole cofferdam is smaller, a cofferdam and floating bridge combined mode is adopted to replace a traditional cofferdam and trestle combined mode for construction, and compared with a trestle, the floating bridge is convenient to assemble and disassemble, lower in manufacturing cost and capable of being repeatedly used.
本发明公开了一种无栈桥的水上桥梁桩基及承台施工方法,该施工方法采用围堰和浮桥相结合的方式实现无栈桥的施工作业,所述围堰在水中圈出施工区域,在施工区域的内部进行桩基和承台的施工;本发明中围堰采用菱形结构的方式,使得围堰整体受到的水流冲击力更小,采用围堰加浮桥的方式代替传统的围堰加栈桥的方式进行施工,浮桥相对于栈桥来说,不仅便于进行安装和拆卸,而且造价更低,也能够进行重复的使用。
Trestle-free overwater bridge pile foundation and bearing platform construction method
一种无栈桥的水上桥梁桩基及承台施工方法
HUANG NING (Autor:in) / LIU GUOQIANG (Autor:in) / ZHANG MENG (Autor:in) / ZHANG QINGMING (Autor:in) / DIAO JI (Autor:in) / CHEN YONG (Autor:in) / ZENG XIAO (Autor:in) / LI HUIYING (Autor:in)
27.10.2020
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2022
|Pipe pile sinking construction method for overwater trestle
Europäisches Patentamt | 2023
|Overwater multi-platform pile foundation construction method
Europäisches Patentamt | 2024
|Innovative Overwater Trestle Reconstruction
British Library Conference Proceedings | 2000
|Construction method of overwater bridge main pier bearing platform
Europäisches Patentamt | 2024
|