Rapid construction system and method for reinforced concrete cast-in-place circular drainage inspection well light formwork
The invention relates to a rapid construction system and method for a reinforced concrete cast-in-place circular drainage inspection well light formwork. The rapid construction system for the reinforced concrete cast-in-place circular drainage inspection well light formwork comprises an outer formwork and an inner formwork, four sets of first fixing devices are arranged at the bottom of the outerformwork, and four sets of second fixing devices are arranged at the bottom of the inner formwork; each set of first fixing device comprises a first strip-shaped groove, a second strip-shaped groove and a first abutting rod; a strip-shaped through hole is formed in the bottom of each second strip-shaped groove; two first anchoring parts are arranged in each strip-shaped through hole in a sliding manner; and a first abutting assembly is arranged between each first anchoring part and the corresponding first abutting rod. The rapid construction method comprises the following steps that the bottomend of the outer formwork is inserted into an outer formwork groove, and the outer formwork is fixed through the first anchoring parts; the bottom end of the inner formwork is inserted into an innerformwork groove, and the inner formwork is fixed through second anchoring parts; grouting is conducted after fixing is completed; and the outer formwork and the inner formwork are respectively disassembled to form an inspection well. The rapid construction system and method have the effect of facilitating repeated utilization of a combined formwork.
本申请涉及钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统及方法,钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统包括外模以及内模,外模底部设置有四组第一固定装置,内模底部设置有四组第二固定装置;每组第一固定装置包括第一条形槽、第二条形槽以及第一抵压杆;第二条形槽底部开设有条形通孔;条形通孔内滑移设置有两个第一锚固件;每个第一锚固件与第一抵压杆之间设置有第一抵压组件。快速施工方法包括如下步骤:将外模底端插入外模槽内,通过第一锚固件对外模进行固定;将内模底端插入内模槽内,通过第二锚固件对内模进行固定;固定完成后进行注浆;分别拆卸外模和内模形成检查井。本申请具有便于组合模板重复利用的效果。
Rapid construction system and method for reinforced concrete cast-in-place circular drainage inspection well light formwork
The invention relates to a rapid construction system and method for a reinforced concrete cast-in-place circular drainage inspection well light formwork. The rapid construction system for the reinforced concrete cast-in-place circular drainage inspection well light formwork comprises an outer formwork and an inner formwork, four sets of first fixing devices are arranged at the bottom of the outerformwork, and four sets of second fixing devices are arranged at the bottom of the inner formwork; each set of first fixing device comprises a first strip-shaped groove, a second strip-shaped groove and a first abutting rod; a strip-shaped through hole is formed in the bottom of each second strip-shaped groove; two first anchoring parts are arranged in each strip-shaped through hole in a sliding manner; and a first abutting assembly is arranged between each first anchoring part and the corresponding first abutting rod. The rapid construction method comprises the following steps that the bottomend of the outer formwork is inserted into an outer formwork groove, and the outer formwork is fixed through the first anchoring parts; the bottom end of the inner formwork is inserted into an innerformwork groove, and the inner formwork is fixed through second anchoring parts; grouting is conducted after fixing is completed; and the outer formwork and the inner formwork are respectively disassembled to form an inspection well. The rapid construction system and method have the effect of facilitating repeated utilization of a combined formwork.
本申请涉及钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统及方法,钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统包括外模以及内模,外模底部设置有四组第一固定装置,内模底部设置有四组第二固定装置;每组第一固定装置包括第一条形槽、第二条形槽以及第一抵压杆;第二条形槽底部开设有条形通孔;条形通孔内滑移设置有两个第一锚固件;每个第一锚固件与第一抵压杆之间设置有第一抵压组件。快速施工方法包括如下步骤:将外模底端插入外模槽内,通过第一锚固件对外模进行固定;将内模底端插入内模槽内,通过第二锚固件对内模进行固定;固定完成后进行注浆;分别拆卸外模和内模形成检查井。本申请具有便于组合模板重复利用的效果。
Rapid construction system and method for reinforced concrete cast-in-place circular drainage inspection well light formwork
钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统及方法
CHEN ZHAOYU (Autor:in) / WANG CHUANWEN (Autor:in) / LIU DAOXIA (Autor:in)
10.11.2020
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Construction method of circular inspection well formwork
Europäisches Patentamt | 2021
|Cast-in-place reinforced concrete floor formwork structure
Europäisches Patentamt | 2021
|