Construction method for land reclamation by belt type sand blowing ship
The invention discloses a construction method for land reclamation by a belt type sand blowing ship. The construction method comprises the following steps that 1, a sand dam is constructed on the edgeof a construction area through the belt type sand blowing ship, and a sand dam surrounding area is formed; 2, a plurality of grid-shaped reclamation unit blocks are set out and divided in the sand dam surrounding area; 3, the sand blowing ship is fully loaded with sand materials to reach the sand dam surrounding area, two anchors and anchor chains of a bow are used for positioning at the positions away from the reclamation unit blocks by a certain distance, and then a belt conveyor head of the sand blowing ship evenly swings left and right in the reclamation unit blocks for sand throwing; 4,the sand blowing ship leaves the sand dam surrounding area and reaches a sand mining area, and sand suction and cabin loading are carried out at the designated position through a sand suction pipe; 5,after a cabin of the sand blowing ship is fully loaded, the sand blowing ship sails to the sand dam surrounding area, and sand throwing construction of the next reclamation unit block to be thrown and filled is carried out; and 6, the step 3 to the step 5 are repeated until sand throwing construction of all the reclamation unit blocks in the sand dam surrounding area is completed. According to the construction method, uniform ballasting of a land area is ensured.
本发明公开了一种皮带式吹砂船吹填成陆的施工方法,包括以下步骤:步骤一,通过皮带式吹砂船在施工区域的边缘构筑砂坝,形成砂坝围区;步骤二,在砂坝围区内放样划分多个网格形的吹填单元块;步骤三,吹砂船满载砂料抵达砂坝围区,并在距吹填单元块一定距离处利用船艏的两个锚和锚链进行定位,然后吹砂船的皮带机机头在吹填单元块内均匀左右摆动进行抛砂;步骤四,吹砂船驶离砂坝围区,抵达采砂区,在指定位置用吸砂管进行吸砂装舱;步骤五,吹砂船的船舱满载后再航行至砂坝围区,进行后一个待抛填的吹填单元块的抛砂施工;步骤六,重复步骤三至步骤五,直至完成砂坝围区内所有的吹填单元块抛砂施工。本发明的施工方法确保了成陆区均匀压载。
Construction method for land reclamation by belt type sand blowing ship
The invention discloses a construction method for land reclamation by a belt type sand blowing ship. The construction method comprises the following steps that 1, a sand dam is constructed on the edgeof a construction area through the belt type sand blowing ship, and a sand dam surrounding area is formed; 2, a plurality of grid-shaped reclamation unit blocks are set out and divided in the sand dam surrounding area; 3, the sand blowing ship is fully loaded with sand materials to reach the sand dam surrounding area, two anchors and anchor chains of a bow are used for positioning at the positions away from the reclamation unit blocks by a certain distance, and then a belt conveyor head of the sand blowing ship evenly swings left and right in the reclamation unit blocks for sand throwing; 4,the sand blowing ship leaves the sand dam surrounding area and reaches a sand mining area, and sand suction and cabin loading are carried out at the designated position through a sand suction pipe; 5,after a cabin of the sand blowing ship is fully loaded, the sand blowing ship sails to the sand dam surrounding area, and sand throwing construction of the next reclamation unit block to be thrown and filled is carried out; and 6, the step 3 to the step 5 are repeated until sand throwing construction of all the reclamation unit blocks in the sand dam surrounding area is completed. According to the construction method, uniform ballasting of a land area is ensured.
本发明公开了一种皮带式吹砂船吹填成陆的施工方法,包括以下步骤:步骤一,通过皮带式吹砂船在施工区域的边缘构筑砂坝,形成砂坝围区;步骤二,在砂坝围区内放样划分多个网格形的吹填单元块;步骤三,吹砂船满载砂料抵达砂坝围区,并在距吹填单元块一定距离处利用船艏的两个锚和锚链进行定位,然后吹砂船的皮带机机头在吹填单元块内均匀左右摆动进行抛砂;步骤四,吹砂船驶离砂坝围区,抵达采砂区,在指定位置用吸砂管进行吸砂装舱;步骤五,吹砂船的船舱满载后再航行至砂坝围区,进行后一个待抛填的吹填单元块的抛砂施工;步骤六,重复步骤三至步骤五,直至完成砂坝围区内所有的吹填单元块抛砂施工。本发明的施工方法确保了成陆区均匀压载。
Construction method for land reclamation by belt type sand blowing ship
一种皮带式吹砂船吹填成陆的施工方法
MO JIANBO (Autor:in) / YU ZHENGWEI (Autor:in) / WANG QIANG (Autor:in) / XU FEI (Autor:in) / DING XIONGJIAN (Autor:in) / LU JIN (Autor:in) / SUN PENGPENG (Autor:in) / ZHAO BIAO (Autor:in) / LI SHAOJUN (Autor:in) / ZHOU JIACHENG (Autor:in)
25.12.2020
Patent
Elektronische Ressource
Chinesisch
Construction method for improving sand blowing efficiency of sand blowing pump
Europäisches Patentamt | 2024
|Shear Strength of Clay - Sand Mixtures in Sand Capping Method of Land Reclamation
British Library Conference Proceedings | 1997
|Engineering Index Backfile | 1949
|