Cast-in-place concrete construction process for EPS steel wire mesh frame plate
The invention relates to a cast-in-place concrete construction process for an EPS steel wire mesh frame plate. According to the cast-in-place concrete construction process, a following EPS steel wiremesh frame plate construction device is adopted. The EPS steel wire mesh frame plate construction device comprises an inner blocking frame, an outer blocking frame, a supporting mechanism and a locking mechanism. By adopting the EPS steel wire mesh frame plate construction device, the cast-in-place concrete construction process comprises the following steps of S1, preparation before construction;S2, locking the inner blocking frame; S3, locking the outer blocking frame; and S4, pouring concrete. According to the cast-in-place concrete construction process for the EPS steel wire mesh frame plate, the problems that when the prior concrete external thermal insulation system is constructed, EPS plates cannot be effectively positioned, so that the EPS plates are displaced during concrete pouring, no anchoring exists between the EPS plates and concrete after thermal insulation wall bodies are formed, the hidden danger that the EPS plates fall off in the later period is caused, steel bars cannot be inserted between the thermal insulation wall bodies, and the stability and the strength of the thermal insulation wall bodies are poor are solved.
本发明涉及一种EPS钢丝网架板现浇混凝土施工工艺,该EPS钢丝网架板现浇混凝土施工工艺采用如下EPS钢丝网架板施工装置,EPS钢丝网架板施工装置包括内挡架、外挡架、支撑机构和锁定机构;采用上述EPS钢丝网架板施工装置对EPS钢丝网架板现浇混凝土的施工工艺,包括以下步骤:S1、施工前准备;S2、内挡架锁定;S3、外挡架锁定;S4、混凝土浇筑。本发明可以解决现有混凝土外保温系统进行施工时存在的以下问题:EPS板无法进行有效定位,使得在混凝土浇筑时EPS板发生位移,保温墙体成型后EPS板与混凝土之间无锚固,造成后期EPS板有脱落的隐患,保温墙体之间无法进行钢筋的插接,使得保温墙体的稳定性与强度较差。
Cast-in-place concrete construction process for EPS steel wire mesh frame plate
The invention relates to a cast-in-place concrete construction process for an EPS steel wire mesh frame plate. According to the cast-in-place concrete construction process, a following EPS steel wiremesh frame plate construction device is adopted. The EPS steel wire mesh frame plate construction device comprises an inner blocking frame, an outer blocking frame, a supporting mechanism and a locking mechanism. By adopting the EPS steel wire mesh frame plate construction device, the cast-in-place concrete construction process comprises the following steps of S1, preparation before construction;S2, locking the inner blocking frame; S3, locking the outer blocking frame; and S4, pouring concrete. According to the cast-in-place concrete construction process for the EPS steel wire mesh frame plate, the problems that when the prior concrete external thermal insulation system is constructed, EPS plates cannot be effectively positioned, so that the EPS plates are displaced during concrete pouring, no anchoring exists between the EPS plates and concrete after thermal insulation wall bodies are formed, the hidden danger that the EPS plates fall off in the later period is caused, steel bars cannot be inserted between the thermal insulation wall bodies, and the stability and the strength of the thermal insulation wall bodies are poor are solved.
本发明涉及一种EPS钢丝网架板现浇混凝土施工工艺,该EPS钢丝网架板现浇混凝土施工工艺采用如下EPS钢丝网架板施工装置,EPS钢丝网架板施工装置包括内挡架、外挡架、支撑机构和锁定机构;采用上述EPS钢丝网架板施工装置对EPS钢丝网架板现浇混凝土的施工工艺,包括以下步骤:S1、施工前准备;S2、内挡架锁定;S3、外挡架锁定;S4、混凝土浇筑。本发明可以解决现有混凝土外保温系统进行施工时存在的以下问题:EPS板无法进行有效定位,使得在混凝土浇筑时EPS板发生位移,保温墙体成型后EPS板与混凝土之间无锚固,造成后期EPS板有脱落的隐患,保温墙体之间无法进行钢筋的插接,使得保温墙体的稳定性与强度较差。
Cast-in-place concrete construction process for EPS steel wire mesh frame plate
一种EPS钢丝网架板现浇混凝土施工工艺
ZHU BINXIANG (Autor:in) / XU LEI (Autor:in)
22.01.2021
Patent
Elektronische Ressource
Chinesisch
Construction supporting device for steel frame structure cast-in-place concrete floor
Europäisches Patentamt | 2020
|Adjustable steel membrane frame cast-in-place concrete reverse ridge construction method
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2024
|Concrete track plate of steel plate and wire mesh structure
Europäisches Patentamt | 2021
|