Unmanned vibration roller earthwork diking construction method
The invention provides an unmanned vibration roller earthwork diking construction method. The unmanned vibration roller earthwork diking construction method comprises the following steps that S1, field data are collected; S2, a rolling compaction test is carried out; S3, rolling compaction parameters are set; S4, a foundation surface is leveled and compacted; S5, soil materials are laid; S6, unmanned vibration roller operation construction is carried out; and S7, construction is completed. When the unmanned vibration roller earthwork diking construction method is adopted for earthwork filling,the labor cost of a vibration roller driver can be reduced, an unmanned vibration roller intelligently sets the rolling parameters through platform control, the rolling percent of pass within the range is close to 100%, and the problem of secondary rework caused by misoperation of the driver is effectively solved. In the time period with the short construction period, 24-hour uninterrupted construction can be achieved through the unmanned vibration roller, and meanwhile, the construction quality is guaranteed.
一种无人驾驶振动碾土方筑堤施工方法,包括以下步骤:步骤S1:现场数据采集;步骤S2:碾压试验;步骤S3:碾压参数设置;步骤S4:建基面平整压实;步骤S5:土料铺筑;步骤S6:无人驾驶振动碾作业施工;步骤S7:施工完成。采用本施工工法进行土方填筑,可以减少振动碾驾驶员的人工费用,且无人振动碾通过平台控制智能设置碾压参数,范围内碾压合格率接近100%,有效避免了由于驾驶员操作不当造成的二次返工问题。在工期紧张的时段,无人振动碾可以达到24小时不间断施工同时保证施工质量。
Unmanned vibration roller earthwork diking construction method
The invention provides an unmanned vibration roller earthwork diking construction method. The unmanned vibration roller earthwork diking construction method comprises the following steps that S1, field data are collected; S2, a rolling compaction test is carried out; S3, rolling compaction parameters are set; S4, a foundation surface is leveled and compacted; S5, soil materials are laid; S6, unmanned vibration roller operation construction is carried out; and S7, construction is completed. When the unmanned vibration roller earthwork diking construction method is adopted for earthwork filling,the labor cost of a vibration roller driver can be reduced, an unmanned vibration roller intelligently sets the rolling parameters through platform control, the rolling percent of pass within the range is close to 100%, and the problem of secondary rework caused by misoperation of the driver is effectively solved. In the time period with the short construction period, 24-hour uninterrupted construction can be achieved through the unmanned vibration roller, and meanwhile, the construction quality is guaranteed.
一种无人驾驶振动碾土方筑堤施工方法,包括以下步骤:步骤S1:现场数据采集;步骤S2:碾压试验;步骤S3:碾压参数设置;步骤S4:建基面平整压实;步骤S5:土料铺筑;步骤S6:无人驾驶振动碾作业施工;步骤S7:施工完成。采用本施工工法进行土方填筑,可以减少振动碾驾驶员的人工费用,且无人振动碾通过平台控制智能设置碾压参数,范围内碾压合格率接近100%,有效避免了由于驾驶员操作不当造成的二次返工问题。在工期紧张的时段,无人振动碾可以达到24小时不间断施工同时保证施工质量。
Unmanned vibration roller earthwork diking construction method
一种无人驾驶振动碾土方筑堤施工方法
WANG JIANWEI (Autor:in) / ZHANG MINGLIANG (Autor:in) / LIU YANKANG (Autor:in) / TONG TAO (Autor:in) / LU TENG (Autor:in) / LIU XUELI (Autor:in) / GUO SHILING (Autor:in) / TIAN XIAO (Autor:in) / HAN FUZUO (Autor:in) / JIN LINGSHI (Autor:in)
05.02.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
EARTHWORK ROLLER AND METHOD OF OPERATING EARTHWORK ROLLER