Mounting construction method of shock insulation support
The invention discloses a mounting construction method of a shock insulation support, which comprises the following steps: S1, erecting an abutment template; S2, manufacturing a steel column frame: welding the multiple hollow steel columns to form the steel column frame in a reinforcement cage shape, and placing the steel column frame in the abutment formwork; S3, erecting a steel embedded plate;S4, pouring concrete integrally into the steel pre-buried steel plate and the abutment; S5, forming connecting positioning holes corresponding to a plurality of steel columns on the steel column framein a base plate of the shock insulation support; S6, pouring concrete into the top ends of the steel columns corresponding to the connecting positioning holes in the base plate, reserving a cavity inone end, and carving internal fastening threads spirally on the inner walls of the cavities of the steel columns; and S7, installing a damping seat. According to the construction and installation method, concrete is poured through the hollow steel column, the supporting strength of the abutment is effectively improved, the connecting strength of the damping support and the abutment can be improved through the cavity reserved in the top of the steel column and connected with the damping support, the damping support is installed and positioned, installation is convenient and fast, and efficiency is high.
本发明公开了一种隔震支座的安装施工方法,包括以下步骤,S1:架设墩台模板;S2:制作钢柱架:将多个中空的钢柱之间通过焊接制成钢筋笼形状的钢柱架并放置在墩台模板内;S3架设钢预埋板;S4:将钢预埋钢板与墩台一体式浇筑混凝土;S5:在隔震支座的底座板上开设于钢柱架上的几个钢柱相对应的连接定位孔;S6:将与底座板上连接定位孔对应的几个钢柱顶端内浇筑混凝土并预留一端空腔且钢柱空腔处的内壁上旋刻内紧固螺纹;S7:安装减震座。本发明施工安装方法利用中空的钢柱浇筑混凝土而有效增加其墩台的支撑强度而钢柱顶部预留连接减震支座的空腔可增加减震支座与墩台的连接强度并对减震支座安装定位,安装便捷且效率较高。
Mounting construction method of shock insulation support
The invention discloses a mounting construction method of a shock insulation support, which comprises the following steps: S1, erecting an abutment template; S2, manufacturing a steel column frame: welding the multiple hollow steel columns to form the steel column frame in a reinforcement cage shape, and placing the steel column frame in the abutment formwork; S3, erecting a steel embedded plate;S4, pouring concrete integrally into the steel pre-buried steel plate and the abutment; S5, forming connecting positioning holes corresponding to a plurality of steel columns on the steel column framein a base plate of the shock insulation support; S6, pouring concrete into the top ends of the steel columns corresponding to the connecting positioning holes in the base plate, reserving a cavity inone end, and carving internal fastening threads spirally on the inner walls of the cavities of the steel columns; and S7, installing a damping seat. According to the construction and installation method, concrete is poured through the hollow steel column, the supporting strength of the abutment is effectively improved, the connecting strength of the damping support and the abutment can be improved through the cavity reserved in the top of the steel column and connected with the damping support, the damping support is installed and positioned, installation is convenient and fast, and efficiency is high.
本发明公开了一种隔震支座的安装施工方法,包括以下步骤,S1:架设墩台模板;S2:制作钢柱架:将多个中空的钢柱之间通过焊接制成钢筋笼形状的钢柱架并放置在墩台模板内;S3架设钢预埋板;S4:将钢预埋钢板与墩台一体式浇筑混凝土;S5:在隔震支座的底座板上开设于钢柱架上的几个钢柱相对应的连接定位孔;S6:将与底座板上连接定位孔对应的几个钢柱顶端内浇筑混凝土并预留一端空腔且钢柱空腔处的内壁上旋刻内紧固螺纹;S7:安装减震座。本发明施工安装方法利用中空的钢柱浇筑混凝土而有效增加其墩台的支撑强度而钢柱顶部预留连接减震支座的空腔可增加减震支座与墩台的连接强度并对减震支座安装定位,安装便捷且效率较高。
Mounting construction method of shock insulation support
一种隔震支座的安装施工方法
YAN XINCHAO (Autor:in) / LIU WENBIN (Autor:in) / REN HONGSHUANG (Autor:in) / LIU JINGSONG (Autor:in) / LI WEI (Autor:in) / ZHANG XIANG (Autor:in) / ZHANG LINGXIANG (Autor:in)
26.02.2021
Patent
Elektronische Ressource
Chinesisch
Accurate mounting method for building shock insulation support
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2022
|Shock insulation support mounting and positioning frame
Europäisches Patentamt | 2021
|Mounting structure for eliminating lift-off of shock insulation support and construction method
Europäisches Patentamt | 2023
|High-rise building shock insulation support and mounting method
Europäisches Patentamt | 2024
|