The invention relates to a curtain grouting construction method. The curtain grouting construction method comprises the construction steps that drilling, hole flushing, water pressing experiment and grouting are conducted, in the drilling process, a track, a bearing table arranged on the track and a moving mechanism arranged between the bearing table and the track are included, the track is laid according to the drilling direction, the track is parallel to a scribed line, the bearing table is installed on the track, then a drilling machine is placed on the track, drilling work is conducted, and after each time of drilling is completed, the moving mechanism drives the bearing table and the drilling machine to move forwards, and then next time of drilling is conducted. The curtain grouting construction method has the effect of improving the accuracy of the drilling machine moving to the next drilling position each time.
本申请涉及一种帷幕灌浆施工方法,其施工步骤为:钻孔、冲洗孔、压水实验和灌浆,在钻孔中,包括轨道、设置在轨道上的承载台以及设置在承载台与轨道之间的移动机构,先根据钻孔的方向铺设轨道,使轨道与划线平行,并将承载台安装到轨道上,再将钻机放置到轨道上后,进行钻孔工作,每完成一次钻孔后使移动机构带动承载台和钻机向前移动后再进行下一次钻孔。本申请具有了提高钻机每一次移动至下一个钻孔位置的准确性的效果。
Curtain grouting construction method
The invention relates to a curtain grouting construction method. The curtain grouting construction method comprises the construction steps that drilling, hole flushing, water pressing experiment and grouting are conducted, in the drilling process, a track, a bearing table arranged on the track and a moving mechanism arranged between the bearing table and the track are included, the track is laid according to the drilling direction, the track is parallel to a scribed line, the bearing table is installed on the track, then a drilling machine is placed on the track, drilling work is conducted, and after each time of drilling is completed, the moving mechanism drives the bearing table and the drilling machine to move forwards, and then next time of drilling is conducted. The curtain grouting construction method has the effect of improving the accuracy of the drilling machine moving to the next drilling position each time.
本申请涉及一种帷幕灌浆施工方法,其施工步骤为:钻孔、冲洗孔、压水实验和灌浆,在钻孔中,包括轨道、设置在轨道上的承载台以及设置在承载台与轨道之间的移动机构,先根据钻孔的方向铺设轨道,使轨道与划线平行,并将承载台安装到轨道上,再将钻机放置到轨道上后,进行钻孔工作,每完成一次钻孔后使移动机构带动承载台和钻机向前移动后再进行下一次钻孔。本申请具有了提高钻机每一次移动至下一个钻孔位置的准确性的效果。
Curtain grouting construction method
一种帷幕灌浆施工方法
GUO GUANG (Autor:in) / ZHOU JIANPING (Autor:in) / WANG XIUYONG (Autor:in) / ZHENG LILI (Autor:in)
26.03.2021
Patent
Elektronische Ressource
Chinesisch
Construction method for composite grouting waterproof curtain
Europäisches Patentamt | 2015
|Construction method for dam anti-seepage curtain grouting
Europäisches Patentamt | 2024
|