High-precision aluminum frame wood formwork construction method
The invention relates to a high-precision aluminum frame wood formwork construction method. The method comprises the steps that 1, technical preparation is conducted; 2, field preparation is conducted; 3, a shear wall formwork is installed; 4, an inclined support and a wall top side form are mounted; 5, a beam mold is installed; 6, floor installation is conducted; 7, a formwork is mounted at the joint of the beam plate and a cylinder; 8, a hole and a stair formwork are mounted; 9, a beam side mold is reinforced; 10, an aluminum mold is removed; 11, aluminum frame wood formwork construction is matched with other types of work. A supporting system capable of achieving early dismantling is arranged, when the concrete reaches the formwork dismantling strength, the supporting system can be dismantled except for a single supporting top and an early dismantling head, continuous construction of an upper-layer structure is guaranteed, turnover use of the formwork can be accelerated, the one-time input amount of the formwork can be greatly reduced, and the formwork configuration amount is reduced.
本发明涉及一种高精度的铝框木模板建造方法,步骤一:技术准备;步骤2、现场准备;步骤3、剪力墙模板安装;步骤4、斜向支撑和墙顶边模安装;步骤5、梁模安装;步骤6、楼板安装;步骤7、梁板与圆柱接口处模板安装;步骤8、洞口、楼梯模板安装;步骤9、梁侧模加固:步骤10、铝模拆除;步骤11、铝框木模板施工与其他工种配合;本发明上能够实现早拆的支撑系统,当混凝土达到拆模强度时,除单支顶和早拆头外,其余均可拆除,既保证上层结构连续施工又能加速模板周转使用,可以大量节省模板一次投入量,减少模板配置量。
High-precision aluminum frame wood formwork construction method
The invention relates to a high-precision aluminum frame wood formwork construction method. The method comprises the steps that 1, technical preparation is conducted; 2, field preparation is conducted; 3, a shear wall formwork is installed; 4, an inclined support and a wall top side form are mounted; 5, a beam mold is installed; 6, floor installation is conducted; 7, a formwork is mounted at the joint of the beam plate and a cylinder; 8, a hole and a stair formwork are mounted; 9, a beam side mold is reinforced; 10, an aluminum mold is removed; 11, aluminum frame wood formwork construction is matched with other types of work. A supporting system capable of achieving early dismantling is arranged, when the concrete reaches the formwork dismantling strength, the supporting system can be dismantled except for a single supporting top and an early dismantling head, continuous construction of an upper-layer structure is guaranteed, turnover use of the formwork can be accelerated, the one-time input amount of the formwork can be greatly reduced, and the formwork configuration amount is reduced.
本发明涉及一种高精度的铝框木模板建造方法,步骤一:技术准备;步骤2、现场准备;步骤3、剪力墙模板安装;步骤4、斜向支撑和墙顶边模安装;步骤5、梁模安装;步骤6、楼板安装;步骤7、梁板与圆柱接口处模板安装;步骤8、洞口、楼梯模板安装;步骤9、梁侧模加固:步骤10、铝模拆除;步骤11、铝框木模板施工与其他工种配合;本发明上能够实现早拆的支撑系统,当混凝土达到拆模强度时,除单支顶和早拆头外,其余均可拆除,既保证上层结构连续施工又能加速模板周转使用,可以大量节省模板一次投入量,减少模板配置量。
High-precision aluminum frame wood formwork construction method
高精度的铝框木模板建造方法
RAO WUBIN (Autor:in) / ZHANG YU (Autor:in) / GONG JIN (Autor:in) / CHEN LIANJIAN (Autor:in) / HUANG YIFAN (Autor:in) / XIANG YONG (Autor:in)
09.04.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
Aluminum-wood combined formwork reinforcing construction method
Europäisches Patentamt | 2023
|Aluminum alloy formwork and wood formwork combined structure and construction method
Europäisches Patentamt | 2023
|Aluminum formwork and wood formwork connecting structure and construction method thereof
Europäisches Patentamt | 2024
|Haunching formwork, formwork frame and construction method of formwork frame
Europäisches Patentamt | 2023
|Aluminum alloy formwork and wood formwork combined structure and construction method
Europäisches Patentamt | 2021
|