Novel platform lifting system
The invention discloses a novel platform lifting system which comprises a main truss system, a tensioning platform, a lifting rod, a cross rod 2, a cross rod 1, a suspension system, an overhanging system, a formwork part, an anchorage device assembly, a guardrail and an overhanging rod. A hanging rod finish rolling deformed steel bar hanging mode is adopted, a hanging system is installed on a main truss of a hanging basket main truss system, a finish rolling deformed steel bar hanging rod is adopted for hanging a tensioning platform, and a chain block or a hydraulic jack is used for adjusting the platform up and down; the hanging basket lifting part comprises two hanging rods, the bottoms of the hanging rods are connected with the formwork part, jacks of the same specification or different specifications are arranged at the connecting positions of the hanging rods and the formwork part, and jacks of different specifications are arranged at each hanging point according to the stress, so that the elevation of a bottom formwork is adjusted rapidly in time, the production efficiency is improved, and the construction period is shortened.
本发明公开了一种新型平台升降系统,包括主桁架系统、张拉平台、吊杆、横杆2、横杆1、悬吊系统、悬挑系统、模板部、锚具组件、护栏、悬挑杆。所述本发明采用吊杆精轧螺纹钢悬吊形式,在挂篮主桁架系统的主桁架上安装悬吊系统,采用精轧螺纹钢吊杆将张拉平台进行悬吊,用手拉葫芦或液压千斤顶对平台进行上下调整;挂篮提升部为吊杆,吊杆为两根,吊杆底部连接模板部,在吊杆与模板部的连接位置处设置相同/不同规格的千斤顶,在每个吊点处根据受力大小设置不同规格的千斤顶,以便及时快速地调整底部模板标高,提高生产效率,缩短施工周期。
Novel platform lifting system
The invention discloses a novel platform lifting system which comprises a main truss system, a tensioning platform, a lifting rod, a cross rod 2, a cross rod 1, a suspension system, an overhanging system, a formwork part, an anchorage device assembly, a guardrail and an overhanging rod. A hanging rod finish rolling deformed steel bar hanging mode is adopted, a hanging system is installed on a main truss of a hanging basket main truss system, a finish rolling deformed steel bar hanging rod is adopted for hanging a tensioning platform, and a chain block or a hydraulic jack is used for adjusting the platform up and down; the hanging basket lifting part comprises two hanging rods, the bottoms of the hanging rods are connected with the formwork part, jacks of the same specification or different specifications are arranged at the connecting positions of the hanging rods and the formwork part, and jacks of different specifications are arranged at each hanging point according to the stress, so that the elevation of a bottom formwork is adjusted rapidly in time, the production efficiency is improved, and the construction period is shortened.
本发明公开了一种新型平台升降系统,包括主桁架系统、张拉平台、吊杆、横杆2、横杆1、悬吊系统、悬挑系统、模板部、锚具组件、护栏、悬挑杆。所述本发明采用吊杆精轧螺纹钢悬吊形式,在挂篮主桁架系统的主桁架上安装悬吊系统,采用精轧螺纹钢吊杆将张拉平台进行悬吊,用手拉葫芦或液压千斤顶对平台进行上下调整;挂篮提升部为吊杆,吊杆为两根,吊杆底部连接模板部,在吊杆与模板部的连接位置处设置相同/不同规格的千斤顶,在每个吊点处根据受力大小设置不同规格的千斤顶,以便及时快速地调整底部模板标高,提高生产效率,缩短施工周期。
Novel platform lifting system
一种新型平台升降系统
CHANG JICHANG (Autor:in) / LI YI (Autor:in) / CAO SHULIANG (Autor:in)
16.04.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken