Construction method for crossing construction waste rotary excavating pile
The invention provides a construction method of a crossing construction waste rotary excavating pile. The construction method includes the steps of S1, paying off at a pile position; S2, carrying out consolidation grouting treatment; S3, carrying out supervision and acceptance; S4, placing a rotary drilling rig; S5, carrying out leveling and drilling; S6, crossing a construction waste layer; S7, controlling rock entering depth; S8, cleaning a hole and measuring the depth of the hole; S9, carrying out supervision and acceptance; and S10, carrying out concrete pouring. According to the construction method of the crossing construction waste rotary excavating pile, the construction quality of penetrating through the construction waste rotary excavating pile can be improved, the working efficiency is improved, and the construction period is shortened.
本发明提供一种穿越建筑垃圾旋挖桩施工方法,所述施工方法包括下述步骤:S1、桩位放线;S2、固结注浆处理;S3、监理验收;S4、旋挖钻机就位;S5、调平钻孔;S6、穿越建筑垃圾层;S7、入岩深度控制;S8、清孔测孔深;S9、监理验收;S10、混凝土浇筑。本发明能够提高穿越建筑垃圾旋挖桩的施工质量,提高工作效率,缩短工期。
Construction method for crossing construction waste rotary excavating pile
The invention provides a construction method of a crossing construction waste rotary excavating pile. The construction method includes the steps of S1, paying off at a pile position; S2, carrying out consolidation grouting treatment; S3, carrying out supervision and acceptance; S4, placing a rotary drilling rig; S5, carrying out leveling and drilling; S6, crossing a construction waste layer; S7, controlling rock entering depth; S8, cleaning a hole and measuring the depth of the hole; S9, carrying out supervision and acceptance; and S10, carrying out concrete pouring. According to the construction method of the crossing construction waste rotary excavating pile, the construction quality of penetrating through the construction waste rotary excavating pile can be improved, the working efficiency is improved, and the construction period is shortened.
本发明提供一种穿越建筑垃圾旋挖桩施工方法,所述施工方法包括下述步骤:S1、桩位放线;S2、固结注浆处理;S3、监理验收;S4、旋挖钻机就位;S5、调平钻孔;S6、穿越建筑垃圾层;S7、入岩深度控制;S8、清孔测孔深;S9、监理验收;S10、混凝土浇筑。本发明能够提高穿越建筑垃圾旋挖桩的施工质量,提高工作效率,缩短工期。
Construction method for crossing construction waste rotary excavating pile
一种穿越建筑垃圾旋挖桩施工方法
GUO HAOHAO (Autor:in) / YAN BAOFENG (Autor:in) / QUAN YOUWEI (Autor:in) / CHEN HONGBIN (Autor:in)
30.04.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Europäisches Patentamt | 2022
|Rotary excavating pile construction device and construction method
Europäisches Patentamt | 2023
|Accurate cutting construction method for rotary excavating pile
Europäisches Patentamt | 2022
|Construction process of rotary excavating hole forming construction method pile
Europäisches Patentamt | 2021
|