Grouting sleeve connection type bent cap assembling construction process
The invention provides a grouting sleeve connection type bent cap assembling construction process. The grouting sleeve connection type cover beam assembling construction process comprises the following steps that 1, a bent cap leaves a factory and is marked; 2, the center of a stand column is remeasured; 3, a hoop and an adjusting cushion block are mounted; 4, a bent cap ink line is made; 5, a crane walking shortcut is laid and a crane is selected; 6, trial hoisting of the bent cap is carried out; 7, slurry mixing is conducted and bedding is conducted on the top faces of the stand column; 8, the bent cap is assembled and observed, and 9, bent cap pressing and grouting are carried out. Compared with the prior art, the construction process has the following advantages that the construction time is short, noise pollution and light pollution to a construction site are greatly reduced, traffic interference is reduced, and the safety risk is obviously reduced.
本发明提供灌浆套筒连接式盖梁拼装施工工艺,包括如下步骤:步骤1:盖梁出厂画线;步骤2:立柱中心复测;步骤3:抱箍和调节垫块安装;步骤4:弹盖梁墨线;步骤5:吊机行走便道铺设和吊机选择;步骤6:盖梁试吊;步骤7:拌浆、立柱顶面坐浆;步骤8:盖梁拼装及观测;步骤9:盖梁压、灌浆,与现有技术相比,本发明具有如下的有益效果:施工时间短,对施工现场噪声污染和光污染大幅度减少,减少交通干扰,安全风险明显降低。
Grouting sleeve connection type bent cap assembling construction process
The invention provides a grouting sleeve connection type bent cap assembling construction process. The grouting sleeve connection type cover beam assembling construction process comprises the following steps that 1, a bent cap leaves a factory and is marked; 2, the center of a stand column is remeasured; 3, a hoop and an adjusting cushion block are mounted; 4, a bent cap ink line is made; 5, a crane walking shortcut is laid and a crane is selected; 6, trial hoisting of the bent cap is carried out; 7, slurry mixing is conducted and bedding is conducted on the top faces of the stand column; 8, the bent cap is assembled and observed, and 9, bent cap pressing and grouting are carried out. Compared with the prior art, the construction process has the following advantages that the construction time is short, noise pollution and light pollution to a construction site are greatly reduced, traffic interference is reduced, and the safety risk is obviously reduced.
本发明提供灌浆套筒连接式盖梁拼装施工工艺,包括如下步骤:步骤1:盖梁出厂画线;步骤2:立柱中心复测;步骤3:抱箍和调节垫块安装;步骤4:弹盖梁墨线;步骤5:吊机行走便道铺设和吊机选择;步骤6:盖梁试吊;步骤7:拌浆、立柱顶面坐浆;步骤8:盖梁拼装及观测;步骤9:盖梁压、灌浆,与现有技术相比,本发明具有如下的有益效果:施工时间短,对施工现场噪声污染和光污染大幅度减少,减少交通干扰,安全风险明显降低。
Grouting sleeve connection type bent cap assembling construction process
灌浆套筒连接式盖梁拼装施工工艺
NING YINGJIE (Autor:in) / GONG SHIWEN (Autor:in) / LOU SHUZHEN (Autor:in) / HUANG YIHAN (Autor:in) / ZHAO YINGCHAO (Autor:in) / BAI LIHUI (Autor:in) / CHEN XUGUANG (Autor:in) / PAN LONGSHENG (Autor:in) / LI QINGYUN (Autor:in) / LI JIAQI (Autor:in)
22.06.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Grouting sleeve connection type bent cap integral prefabrication construction process
Europäisches Patentamt | 2021
|PC structure grouting sleeve connection construction method
Europäisches Patentamt | 2021
|Reinforcing steel bar sleeve grouting connection process
Europäisches Patentamt | 2021
|Multifunctional assembly type building connection grouting sleeve
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2020
|