Track anchoring device for hanging basket construction
The invention discloses a track anchoring device for hanging basket construction. The track anchoring device comprises a first track anchoring rib, a track, a track bearing beam, a second track anchoring rib, a beam body, first I-shaped steel, second I-shaped steel, a gap, a nut, a gasket, mounting positioning holes, a positioning part and a mounting part. According to the track anchoring device for hanging basket construction, the purpose of anchoring a hanging basket track is achieved by pre-tightening the first track anchoring rib and the second track anchoring rib, after construction is completed, only the nut needs to be reversely rotated, and then the first track anchoring rib and the second track anchoring rib are pulled out of the mounting positioning holes; and therefore, the first track anchoring rib and the second track anchoring rib which are drawn out are recycled to a lower beam section, a cyclic utilization construction mode is formed; about 5-10 t of unrecyclable deformed steel bars which are used previously can be saved for each continuous beam; steel bar heads do not need to be cleaned after beam section pouring is completed, so that universality is enhanced; and the track anchoring device can be recycled to different continuous beams, so that material consumption is reduced.
本发明公开了一种挂篮施工用轨道锚固装置,包括第一轨道锚固筋、轨道、轨道垫梁、第二轨道锚固筋、梁体、第一工字钢、第二工字钢、间隙、螺母、垫片、安装定位孔、定位部、安装部。所述本发明通过预紧第一轨道锚固筋、第二轨道锚固筋达到锚固挂篮轨道的目的,施工完毕后仅需反向旋转螺母,然后将第一轨道锚固筋、第二轨道锚固筋抽出安装定位孔,由此将抽出的第一轨道锚固筋、第二轨道锚固筋循环利用到下段梁段,形成循环利用的施工方式,并且每条连续梁可以节约先前使用的不可循环螺纹钢约5‑10t,并且在梁段浇筑完毕后无需清理钢筋头,增强通用性,可循环利用于不同连续梁,减少材料消耗。
Track anchoring device for hanging basket construction
The invention discloses a track anchoring device for hanging basket construction. The track anchoring device comprises a first track anchoring rib, a track, a track bearing beam, a second track anchoring rib, a beam body, first I-shaped steel, second I-shaped steel, a gap, a nut, a gasket, mounting positioning holes, a positioning part and a mounting part. According to the track anchoring device for hanging basket construction, the purpose of anchoring a hanging basket track is achieved by pre-tightening the first track anchoring rib and the second track anchoring rib, after construction is completed, only the nut needs to be reversely rotated, and then the first track anchoring rib and the second track anchoring rib are pulled out of the mounting positioning holes; and therefore, the first track anchoring rib and the second track anchoring rib which are drawn out are recycled to a lower beam section, a cyclic utilization construction mode is formed; about 5-10 t of unrecyclable deformed steel bars which are used previously can be saved for each continuous beam; steel bar heads do not need to be cleaned after beam section pouring is completed, so that universality is enhanced; and the track anchoring device can be recycled to different continuous beams, so that material consumption is reduced.
本发明公开了一种挂篮施工用轨道锚固装置,包括第一轨道锚固筋、轨道、轨道垫梁、第二轨道锚固筋、梁体、第一工字钢、第二工字钢、间隙、螺母、垫片、安装定位孔、定位部、安装部。所述本发明通过预紧第一轨道锚固筋、第二轨道锚固筋达到锚固挂篮轨道的目的,施工完毕后仅需反向旋转螺母,然后将第一轨道锚固筋、第二轨道锚固筋抽出安装定位孔,由此将抽出的第一轨道锚固筋、第二轨道锚固筋循环利用到下段梁段,形成循环利用的施工方式,并且每条连续梁可以节约先前使用的不可循环螺纹钢约5‑10t,并且在梁段浇筑完毕后无需清理钢筋头,增强通用性,可循环利用于不同连续梁,减少材料消耗。
Track anchoring device for hanging basket construction
一种挂篮施工用轨道锚固装置
ZHANG XU (Autor:in) / GE HUI (Autor:in) / WANG QUANLE (Autor:in)
09.07.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Anchoring method for hanging basket during cantilever construction