Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Building outer wall dry hanging stone curtain wall paving construction method
The invention provides a building outer wall dry hanging stone curtain wall paving construction method. The method involves a moving control mechanism, a loading mechanism, a discharging mechanism and a lifting and mounting mechanism. At present, the paving construction of stone curtain walls generally needs a plurality of workers to cooperate with one another, stone panels are adsorbed and fixed by holding suction cups with the hands, then the stone panels are horizontally aligned with the mounting position of a keel frame, and the paving operation is carried out; in the whole process, the requirement for the matching degree of the workers is relatively high; meanwhile, the workers need to work in the air for a long time, so that the danger is relatively high; the labor conditions of constructors are poor, so that the paving difficulty is relatively high, the labor intensity is high, and the paving efficiency and the paving quality are easily affected; the stone panels are stacked together during storage, so that the stone panels are not easy to take and mount; and the stone panels are easy to shake during aerial operation, so that the stone panels collide with one another to be damaged and cannot be used, and the paving cost is increased. By the method, the above problems are solved.
本发明提供了一种建筑外墙干挂石材幕墙铺装施工方法,包括移控机构、装取机构、排放机构和升装机构,现今石材幕墙的铺装施工一般需要多个工人相互配合,通过手持吸盘将石材面板进行吸附固定,然后再将石材面板与龙骨架的安装位置水平对齐,再进行铺装操作,整个过程中,对工人的配合度要求较高,同时工人需要长时间在空中进行作业,危险性比较高,施工人员的劳动条件差,导致铺装难度较大,劳动强度高,极易影响铺装效率以及铺装质量,并且石材面板的存放是堆叠在一起,不容易拿取安装,在空中作业时容易发生晃动,导致石材面板之间发生磕碰,造成石材面板的损坏,从而不能使用,增加铺装成本等问题。
Building outer wall dry hanging stone curtain wall paving construction method
The invention provides a building outer wall dry hanging stone curtain wall paving construction method. The method involves a moving control mechanism, a loading mechanism, a discharging mechanism and a lifting and mounting mechanism. At present, the paving construction of stone curtain walls generally needs a plurality of workers to cooperate with one another, stone panels are adsorbed and fixed by holding suction cups with the hands, then the stone panels are horizontally aligned with the mounting position of a keel frame, and the paving operation is carried out; in the whole process, the requirement for the matching degree of the workers is relatively high; meanwhile, the workers need to work in the air for a long time, so that the danger is relatively high; the labor conditions of constructors are poor, so that the paving difficulty is relatively high, the labor intensity is high, and the paving efficiency and the paving quality are easily affected; the stone panels are stacked together during storage, so that the stone panels are not easy to take and mount; and the stone panels are easy to shake during aerial operation, so that the stone panels collide with one another to be damaged and cannot be used, and the paving cost is increased. By the method, the above problems are solved.
本发明提供了一种建筑外墙干挂石材幕墙铺装施工方法,包括移控机构、装取机构、排放机构和升装机构,现今石材幕墙的铺装施工一般需要多个工人相互配合,通过手持吸盘将石材面板进行吸附固定,然后再将石材面板与龙骨架的安装位置水平对齐,再进行铺装操作,整个过程中,对工人的配合度要求较高,同时工人需要长时间在空中进行作业,危险性比较高,施工人员的劳动条件差,导致铺装难度较大,劳动强度高,极易影响铺装效率以及铺装质量,并且石材面板的存放是堆叠在一起,不容易拿取安装,在空中作业时容易发生晃动,导致石材面板之间发生磕碰,造成石材面板的损坏,从而不能使用,增加铺装成本等问题。
Building outer wall dry hanging stone curtain wall paving construction method
一种建筑外墙干挂石材幕墙铺装施工方法
ZHANG WEIWEI (Autor:in)
06.08.2021
Patent
Elektronische Ressource
Chinesisch
Building dry hanging stone curtain wall paving and seam beautifying construction method
Europäisches Patentamt | 2021
|Dry hanging stone curtain wall construction method and curtain wall structure
Europäisches Patentamt | 2024
|Construction treatment method for dry-hanging stone curtain wall on outer wall of high-rise building
Europäisches Patentamt | 2021
|Installation construction method for building dry hanging stone curtain wall
Europäisches Patentamt | 2021
|