Construction method and formwork of reverse construction method lining wall
The invention discloses a construction method and formwork of a reverse construction method lining wall. A first horizontal plate of a construction formwork of the reverse construction method lining wall can be tightly connected with supporting piles, and a second horizontal plate of the construction formwork of the reverse construction method lining wall can be connected with the lower surface of a floor formwork. According to the scheme of the construction method and formwork of the reverse construction method lining wall, a top beam and the lining wall are constructed at the same time through the concrete of the same grade, and the construction period of the lining wall is greatly shortened; and meanwhile, the connecting position of the lining wall and the top beam can be prevented from cracking, the supporting piles and a Z-shaped formwork are connected into a whole, it is guaranteed that the lining wall is not prone to leaking slurry and cracking, and the overall stability of a foundation pit is improved.
本发明公开了一种逆作法内衬墙的施工方法及模板,其中,逆作法内衬墙的施工模板的第一水平板能够与支护桩紧密连接,逆作法内衬墙的施工模板的第二水平板能够与楼板模板的下表面连接。本方案中冠梁与内衬墙采用同一等级的混凝土同时施工,大大缩短了内衬墙的施工周期,同时能够避免内衬墙与冠梁的连接位置发生开裂,并将支护桩与Z字形模板连接成整体,保证内衬墙不易漏浆开裂,提升基坑的整体稳定性。
Construction method and formwork of reverse construction method lining wall
The invention discloses a construction method and formwork of a reverse construction method lining wall. A first horizontal plate of a construction formwork of the reverse construction method lining wall can be tightly connected with supporting piles, and a second horizontal plate of the construction formwork of the reverse construction method lining wall can be connected with the lower surface of a floor formwork. According to the scheme of the construction method and formwork of the reverse construction method lining wall, a top beam and the lining wall are constructed at the same time through the concrete of the same grade, and the construction period of the lining wall is greatly shortened; and meanwhile, the connecting position of the lining wall and the top beam can be prevented from cracking, the supporting piles and a Z-shaped formwork are connected into a whole, it is guaranteed that the lining wall is not prone to leaking slurry and cracking, and the overall stability of a foundation pit is improved.
本发明公开了一种逆作法内衬墙的施工方法及模板,其中,逆作法内衬墙的施工模板的第一水平板能够与支护桩紧密连接,逆作法内衬墙的施工模板的第二水平板能够与楼板模板的下表面连接。本方案中冠梁与内衬墙采用同一等级的混凝土同时施工,大大缩短了内衬墙的施工周期,同时能够避免内衬墙与冠梁的连接位置发生开裂,并将支护桩与Z字形模板连接成整体,保证内衬墙不易漏浆开裂,提升基坑的整体稳定性。
Construction method and formwork of reverse construction method lining wall
一种逆作法内衬墙的施工方法及模板
LI XINGLANG (Autor:in) / SU WENCAN (Autor:in) / CHEN BO (Autor:in) / XIONG JIANG (Autor:in) / SONG JIEYING (Autor:in) / ZHANG PULIN (Autor:in) / SU LUXUAN (Autor:in)
13.08.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Lining wall construction formwork system and construction method thereof
Europäisches Patentamt | 2024
|Basement lining wall unilateral formwork system and construction method thereof
Europäisches Patentamt | 2023
|Basement border area reverse construction method lining wall construction method
Europäisches Patentamt | 2021
|CURING FORMWORK STRUCTURE AND CONSTRUCTION METHOD OF TUNNEL LINING
Europäisches Patentamt | 2019
|Ultra-deep circular vertical shaft lining wall formwork structure and construction method thereof