Construction stage deployment construction method
The invention discloses a construction stage deployment construction method, and particularly relates to the technical field of construction deployment. According to the technical scheme, the construction stage deployment construction method comprises the following specific steps: S1, pile foundation stage general plane arrangement is conducted, specifically, 1, a main entrance is formed in the west side of a site in the stage, and a riding track with the width of 8 m is arranged on the north side of a foundation pit for vehicles to enter the foundation pit for construction; and 2, two pipe pile temporary storage yards, two mud pits, two steel bar machining areas and two steel bar cage storage yards are arranged on site, and prefabricated pipe piles and cast-in-place piles are constructed at the same time on site. The construction method has the beneficial effects that the project is constructed through the seven stages of pile foundation stage general plane arrangement, first underground stage general plane arrangement, second underground stage general plane arrangement, third underground stage general plane arrangement, overground stage general plane arrangement, first decoration stage general plane arrangement and second decoration stage general plane arrangement, so that the construction period is shortened, the construction cost is reduced, and the construction benefit is improved.
本发明公开了一种施工阶段部署施工方法,具体涉及施工部署技术领域,其技术方案是:包括具体步骤如下:S1,桩基阶段总平面布置:步骤一,此阶段场地西侧设置一个主入口,在基坑的北侧设置一条8m宽马道用于车辆进入基坑施工;步骤二,现场设置2个管桩临时堆场,设置2个泥浆池,2个钢筋加工区,2个钢筋笼堆场,现场预制管桩、灌注桩同时施工,本发明的有益效果是:通过桩基阶段总平面布置、地下阶段一总平面布置、地下阶段二总平面布置、地下阶段三总平面布置、地上阶段总平面布置、装修阶段一总平面布置和装修阶段二总平面布置七个阶段对工程进行施工,不仅缩短了工期,还降低了施工成本以及提高了施工效益。
Construction stage deployment construction method
The invention discloses a construction stage deployment construction method, and particularly relates to the technical field of construction deployment. According to the technical scheme, the construction stage deployment construction method comprises the following specific steps: S1, pile foundation stage general plane arrangement is conducted, specifically, 1, a main entrance is formed in the west side of a site in the stage, and a riding track with the width of 8 m is arranged on the north side of a foundation pit for vehicles to enter the foundation pit for construction; and 2, two pipe pile temporary storage yards, two mud pits, two steel bar machining areas and two steel bar cage storage yards are arranged on site, and prefabricated pipe piles and cast-in-place piles are constructed at the same time on site. The construction method has the beneficial effects that the project is constructed through the seven stages of pile foundation stage general plane arrangement, first underground stage general plane arrangement, second underground stage general plane arrangement, third underground stage general plane arrangement, overground stage general plane arrangement, first decoration stage general plane arrangement and second decoration stage general plane arrangement, so that the construction period is shortened, the construction cost is reduced, and the construction benefit is improved.
本发明公开了一种施工阶段部署施工方法,具体涉及施工部署技术领域,其技术方案是:包括具体步骤如下:S1,桩基阶段总平面布置:步骤一,此阶段场地西侧设置一个主入口,在基坑的北侧设置一条8m宽马道用于车辆进入基坑施工;步骤二,现场设置2个管桩临时堆场,设置2个泥浆池,2个钢筋加工区,2个钢筋笼堆场,现场预制管桩、灌注桩同时施工,本发明的有益效果是:通过桩基阶段总平面布置、地下阶段一总平面布置、地下阶段二总平面布置、地下阶段三总平面布置、地上阶段总平面布置、装修阶段一总平面布置和装修阶段二总平面布置七个阶段对工程进行施工,不仅缩短了工期,还降低了施工成本以及提高了施工效益。
Construction stage deployment construction method
一种施工阶段部署施工方法
LIU JIN (Autor:in) / MO FAN (Autor:in) / WANG ZHENGDONG (Autor:in) / QIAN JINWANG (Autor:in) / ZHU BIN (Autor:in) / LI XIN (Autor:in)
24.09.2021
Patent
Elektronische Ressource
Chinesisch
Quality function deployment in construction
British Library Online Contents | 2007
|Quality function deployment in construction
Online Contents | 2007
|Quality function deployment in construction
Online Contents | 2007
|RFID deployment protocols for indoor construction
Emerald Group Publishing | 2012
|RFID deployment protocols for indoor construction
British Library Online Contents | 2012
|