Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Manual hole digging construction method for cast-in-place pile
The invention discloses a manual hole digging construction method for a cast-in-place pile. The manual hole digging construction method for the cast-in-place pile comprises the following steps that a site around an orifice of a cast-in-place pile hole is mechanically or manually cleaned and leveled; the orifice part of the cast-in-place pile hole is excavated to the rock surface, and then concrete with a certain height is poured along the periphery of the orifice; a rock core around the cast-in-place pile hole is drilled; a central rock mass is excavated; after the central rock mass is lifted out, residual rock masses on the hole wall and the hole bottom are cleaned, and excavation of the layer is completed; and next-layer excavation is conducted till a designed depth is reached, and overall hole digging construction of the cast-in-place pile hole is completed. The manual hole digging construction method for the cast-in-place pile has the advantages of being simple in process, low in cost, high in adaptability and high in construction efficiency.
一种灌注桩人工挖孔施工方法,采用机械或人工清理、平整灌注桩孔孔口周围场地;灌注桩孔孔口部位开挖到岩石面,然后沿孔口周圈浇筑一定高度的混凝土;钻取灌注桩孔周边岩芯;中心岩体开挖;中心岩体吊出后,对孔壁和孔底残留岩体进行清理,完成本层开挖;进行下一层开挖,直至开挖到设计深度,完成灌注桩孔整体挖孔施工。本发明具有工艺简单、成本低、适应性强、施工效率高的优点。
Manual hole digging construction method for cast-in-place pile
The invention discloses a manual hole digging construction method for a cast-in-place pile. The manual hole digging construction method for the cast-in-place pile comprises the following steps that a site around an orifice of a cast-in-place pile hole is mechanically or manually cleaned and leveled; the orifice part of the cast-in-place pile hole is excavated to the rock surface, and then concrete with a certain height is poured along the periphery of the orifice; a rock core around the cast-in-place pile hole is drilled; a central rock mass is excavated; after the central rock mass is lifted out, residual rock masses on the hole wall and the hole bottom are cleaned, and excavation of the layer is completed; and next-layer excavation is conducted till a designed depth is reached, and overall hole digging construction of the cast-in-place pile hole is completed. The manual hole digging construction method for the cast-in-place pile has the advantages of being simple in process, low in cost, high in adaptability and high in construction efficiency.
一种灌注桩人工挖孔施工方法,采用机械或人工清理、平整灌注桩孔孔口周围场地;灌注桩孔孔口部位开挖到岩石面,然后沿孔口周圈浇筑一定高度的混凝土;钻取灌注桩孔周边岩芯;中心岩体开挖;中心岩体吊出后,对孔壁和孔底残留岩体进行清理,完成本层开挖;进行下一层开挖,直至开挖到设计深度,完成灌注桩孔整体挖孔施工。本发明具有工艺简单、成本低、适应性强、施工效率高的优点。
Manual hole digging construction method for cast-in-place pile
一种灌注桩人工挖孔施工方法
DANG PENG (Autor:in) / FAN DANDAN (Autor:in) / HOU JUAN (Autor:in) / FENG XIUMING (Autor:in) / FAN YUHANG (Autor:in) / GAO XINCHI (Autor:in)
08.10.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Manual hole digging pile and construction method of manual hole digging pile
Europäisches Patentamt | 2020
|Construction method of manual hole digging pile and manual hole digging pile
Europäisches Patentamt | 2021
|Manual hole digging pile and construction method of manual hole digging pile
Europäisches Patentamt | 2020
|Construction method for manual hole digging cast-in-place pile in karst area
Europäisches Patentamt | 2022
|