Construction method of 1000t/40m box girder, high-speed railway, girder transporting vehicle and bridge erection machine
The invention discloses a construction method of a 1000t/40m box girder, a high-speed railway, a girder transporting vehicle and a bridge erection machine. The construction method comprises the following steps: the box girder is loaded onto the girder transporting vehicle by adopting a girder lifting machine; the girder transporting vehicle transports the box girder to the tail part of the bridge erecting machine and aligning is performed; the bridge erection machine is matched with the girder transporting vehicle to complete girder jacking, girder taking and girder feeding; and the bridge erection machine completes girder falling. The technical problems that driving is not safe enough, and the labor intensity of workers is large are solved.
本申请公开了一种1000t/40m箱梁的施工方法、高速铁路、运梁车及架桥机。该施工方法包括:采用提梁机将箱梁装至运梁车上;运梁车运输箱梁至架桥机的尾部并对位;架桥机配合运梁车完成顶梁、取梁及喂梁;架桥机完成落梁。本申请解决了行车不够安全,且人员劳动强度大的技术问题。
Construction method of 1000t/40m box girder, high-speed railway, girder transporting vehicle and bridge erection machine
The invention discloses a construction method of a 1000t/40m box girder, a high-speed railway, a girder transporting vehicle and a bridge erection machine. The construction method comprises the following steps: the box girder is loaded onto the girder transporting vehicle by adopting a girder lifting machine; the girder transporting vehicle transports the box girder to the tail part of the bridge erecting machine and aligning is performed; the bridge erection machine is matched with the girder transporting vehicle to complete girder jacking, girder taking and girder feeding; and the bridge erection machine completes girder falling. The technical problems that driving is not safe enough, and the labor intensity of workers is large are solved.
本申请公开了一种1000t/40m箱梁的施工方法、高速铁路、运梁车及架桥机。该施工方法包括:采用提梁机将箱梁装至运梁车上;运梁车运输箱梁至架桥机的尾部并对位;架桥机配合运梁车完成顶梁、取梁及喂梁;架桥机完成落梁。本申请解决了行车不够安全,且人员劳动强度大的技术问题。
Construction method of 1000t/40m box girder, high-speed railway, girder transporting vehicle and bridge erection machine
1000t/40m箱梁的施工方法、高速铁路、运梁车及架桥机
ZHAO ZHENXING (Autor:in) / QIU ZI (Autor:in) / DONG QIJUN (Autor:in) / WANG PENG (Autor:in) / WAN PENG (Autor:in) / WU YANJIANG (Autor:in) / WU MENGYU (Autor:in) / CAO WANHUI (Autor:in) / TANG KUN (Autor:in) / DU JUNLIANG (Autor:in)
05.11.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Girder transporting vehicle and method for carrying bridge girder erection machine
Europäisches Patentamt | 2021
|Bridge girder erection machine and via hole girder erection method of bridge girder erection machine
Europäisches Patentamt | 2024
|Bridge girder erection machine and via hole girder erection method of bridge girder erection machine
Europäisches Patentamt | 2024
|Europäisches Patentamt | 2024
|Railway flat car loaded bridge girder erection machine and girder erection method thereof
Europäisches Patentamt | 2016
|