Movable hanging and hoisting construction method for steel structure fabricated wallboard
The invention relates to the technical field of wallboard hoisting construction, and provides a movable hanging and hoisting construction method for a steel structure fabricated wallboard. The movable hanging and hoisting construction method comprises the following steps that the wallboard is lowered, so that two groups of conical positioning pieces are firstly clamped into grouting sleeves at the two ends of the wallboard, and the wallboard is temporarily positioned; and then three groups of driving pieces on a bottom plate correspondingly drive three groups of abutting rod pieces to abut against the three side surfaces of the wallboard to limit the displacement of the wallboard in the horizontal direction, so that the grouting sleeve can be smoothly sleeved into the connecting steel bar in the subsequent descending process of the wallboard, and the hoisting of the wallboard is simpler and more convenient.
本申请涉及墙板吊装施工的技术领域,提出了一种钢结构装配式墙板可移动悬挂吊装施工方法,本申请通过下放墙板使两组锥形定位件先卡入墙板两端的注浆套管,实现对墙板的暂时定位,再通过底板上的三组驱动件分别驱使三组抵接杆件与墙板的三侧面抵接,限制墙板发生水平方向位移,进而使得后续墙板下放过程中,注浆套管可以顺利地套入连接钢筋,使得墙板的吊装更加简单方便。
Movable hanging and hoisting construction method for steel structure fabricated wallboard
The invention relates to the technical field of wallboard hoisting construction, and provides a movable hanging and hoisting construction method for a steel structure fabricated wallboard. The movable hanging and hoisting construction method comprises the following steps that the wallboard is lowered, so that two groups of conical positioning pieces are firstly clamped into grouting sleeves at the two ends of the wallboard, and the wallboard is temporarily positioned; and then three groups of driving pieces on a bottom plate correspondingly drive three groups of abutting rod pieces to abut against the three side surfaces of the wallboard to limit the displacement of the wallboard in the horizontal direction, so that the grouting sleeve can be smoothly sleeved into the connecting steel bar in the subsequent descending process of the wallboard, and the hoisting of the wallboard is simpler and more convenient.
本申请涉及墙板吊装施工的技术领域,提出了一种钢结构装配式墙板可移动悬挂吊装施工方法,本申请通过下放墙板使两组锥形定位件先卡入墙板两端的注浆套管,实现对墙板的暂时定位,再通过底板上的三组驱动件分别驱使三组抵接杆件与墙板的三侧面抵接,限制墙板发生水平方向位移,进而使得后续墙板下放过程中,注浆套管可以顺利地套入连接钢筋,使得墙板的吊装更加简单方便。
Movable hanging and hoisting construction method for steel structure fabricated wallboard
钢结构装配式墙板可移动悬挂吊装施工方法
XU BINGJIN (Autor:in)
17.12.2021
Patent
Elektronische Ressource
Chinesisch
Movable hanging and hoisting construction method for steel structure fabricated wallboard
Europäisches Patentamt | 2021
|