Construction method of smoke exhaust air pipe externally wrapped with fireproof plate
The invention relates to the technical field of fireproof plate construction, in particular to a construction method of a smoke exhaust air pipe externally wrapped with a fireproof plate. The construction method comprises the following steps that S1, construction preparation is carried out; S2, supports and hangers are installed, Revit software is used for performing optimized arrangement on pipeline arrangement, and the elevations of air pipes are determined according to a civil engineering datum line; S3, the air pipes are connected in pairs; S4, the fireproof plate is installed; S5, the air pipes are hoisted; S6, the air pipes are installed and adjusted; and S7, air leakage testing of the air pipes is carried out, after the air pipes are installed, the air leakage testing needs to be carried out, and according to specifications, the air leakage testing of the air pipes adopts a mode of combining qualitative detection of a light leakage method and quantitative detection of the air leakage testing. According to the construction method, the construction efficiency is improved, the construction difficulty is reduced, the construction period is shortened, the construction cost is saved, the construction quality can be improved, and the obtained economic benefits and social benefits are obvious. The construction method is mainly applied to construction of the smoke exhaust air pipe coated with the fireproof plate.
本发明涉及防火板施工技术领域,更具体而言,涉及外包覆防火板的排烟风管施工方法。包括以下步骤:S1、施工准备;S2、支吊架安装:运用Revit软件对管线布置进行优化排布,参照土建基准线确定风管的标高;S3、风管组对连接;S4、防火板安装;S5、风管吊装;S6、风管安装及调整;S7、风管的漏风量测试:风管安装完毕后需进行漏风量测试,依据规范规定,风管的漏风量检测采用漏光法定性检测和漏风量测试定量检测相结合的方式。该工法提高施工效率、降低施工难度、缩短工期、节约施工费用,并且能够提高施工质量,所取得的经济效益和社会效益明显。本发明主要应用于包覆防火板的排烟风管施工方面。
Construction method of smoke exhaust air pipe externally wrapped with fireproof plate
The invention relates to the technical field of fireproof plate construction, in particular to a construction method of a smoke exhaust air pipe externally wrapped with a fireproof plate. The construction method comprises the following steps that S1, construction preparation is carried out; S2, supports and hangers are installed, Revit software is used for performing optimized arrangement on pipeline arrangement, and the elevations of air pipes are determined according to a civil engineering datum line; S3, the air pipes are connected in pairs; S4, the fireproof plate is installed; S5, the air pipes are hoisted; S6, the air pipes are installed and adjusted; and S7, air leakage testing of the air pipes is carried out, after the air pipes are installed, the air leakage testing needs to be carried out, and according to specifications, the air leakage testing of the air pipes adopts a mode of combining qualitative detection of a light leakage method and quantitative detection of the air leakage testing. According to the construction method, the construction efficiency is improved, the construction difficulty is reduced, the construction period is shortened, the construction cost is saved, the construction quality can be improved, and the obtained economic benefits and social benefits are obvious. The construction method is mainly applied to construction of the smoke exhaust air pipe coated with the fireproof plate.
本发明涉及防火板施工技术领域,更具体而言,涉及外包覆防火板的排烟风管施工方法。包括以下步骤:S1、施工准备;S2、支吊架安装:运用Revit软件对管线布置进行优化排布,参照土建基准线确定风管的标高;S3、风管组对连接;S4、防火板安装;S5、风管吊装;S6、风管安装及调整;S7、风管的漏风量测试:风管安装完毕后需进行漏风量测试,依据规范规定,风管的漏风量检测采用漏光法定性检测和漏风量测试定量检测相结合的方式。该工法提高施工效率、降低施工难度、缩短工期、节约施工费用,并且能够提高施工质量,所取得的经济效益和社会效益明显。本发明主要应用于包覆防火板的排烟风管施工方面。
Construction method of smoke exhaust air pipe externally wrapped with fireproof plate
外包覆防火板的排烟风管施工方法
SUN XUESHUANG (Autor:in) / WANG TAO (Autor:in) / WEI JUN (Autor:in) / FAN HUA (Autor:in) / WANG KEXIN (Autor:in) / LU XIAOPENG (Autor:in)
21.12.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E04G
SCAFFOLDING
,
Baugerüste
/
E04B
Allgemeine Baukonstruktionen
,
GENERAL BUILDING CONSTRUCTIONS
/
G06F
ELECTRIC DIGITAL DATA PROCESSING
,
Elektrische digitale Datenverarbeitung
/
G06Q
Datenverarbeitungssysteme oder -verfahren, besonders angepasst an verwaltungstechnische, geschäftliche, finanzielle oder betriebswirtschaftliche Zwecke, sowie an geschäftsbezogene Überwachungs- oder Voraussagezwecke
,
DATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2024
|Processing technology of special plate for integrated fireproof smoke exhaust air duct
Europäisches Patentamt | 2021
|Construction method of externally-wrapped multi-cavity steel plate concrete composite shear wall
Europäisches Patentamt | 2021
|