Eine Plattform für die Wissenschaft: Bauingenieurwesen, Architektur und Urbanistik
Construction method of entrance and exit fender posts
The invention is suitable for the technical field of station entrance and exit fender post construction, and provides an entrance and exit fender post construction method which comprises the steps that S1, construction preparation is conducted, hole positions are measured, and a pile casing is installed; S2, a drilling machine is placed in place, and drilling is conducted according to the hole positions; S3, lateral anchor pile hole forming; S4, the drilled holes are subjected to hole cleaning and hole forming inspection; S5, a reinforcement cage is manufactured and installed; S6, a guide pipe is installed; S7, the drilled hole is subjected to secondary hole cleaning treatment; S8, pouring concrete; S9, chiseling a pile head; and S10, pile foundation detection. The construction efficiency of the fender post at the entrance and exit of the station can be improved, the cost is saved, the construction safety is high, and the application range is wide.
本发明适用于车站出入口围护桩施工技术领域,提供了一种出入口围护桩的施工方法,所述方法包括步骤:S1、施工准备,测定孔位,并安装护筒;S2、将钻机就位并根据所述孔位进行钻孔;S3、侧向锚桩成孔;S4、对钻好的孔进行清孔及成孔检查;S5、制作并安装钢筋笼;S6、安装导管;S7、对钻好的孔进行二次清孔处理;S8、灌注混凝土;S9、凿桩头;S10、桩基检测。本发明能够提高车站出入口围护桩的施工效率,节约成本,施工的安全性高,使用广泛。
Construction method of entrance and exit fender posts
The invention is suitable for the technical field of station entrance and exit fender post construction, and provides an entrance and exit fender post construction method which comprises the steps that S1, construction preparation is conducted, hole positions are measured, and a pile casing is installed; S2, a drilling machine is placed in place, and drilling is conducted according to the hole positions; S3, lateral anchor pile hole forming; S4, the drilled holes are subjected to hole cleaning and hole forming inspection; S5, a reinforcement cage is manufactured and installed; S6, a guide pipe is installed; S7, the drilled hole is subjected to secondary hole cleaning treatment; S8, pouring concrete; S9, chiseling a pile head; and S10, pile foundation detection. The construction efficiency of the fender post at the entrance and exit of the station can be improved, the cost is saved, the construction safety is high, and the application range is wide.
本发明适用于车站出入口围护桩施工技术领域,提供了一种出入口围护桩的施工方法,所述方法包括步骤:S1、施工准备,测定孔位,并安装护筒;S2、将钻机就位并根据所述孔位进行钻孔;S3、侧向锚桩成孔;S4、对钻好的孔进行清孔及成孔检查;S5、制作并安装钢筋笼;S6、安装导管;S7、对钻好的孔进行二次清孔处理;S8、灌注混凝土;S9、凿桩头;S10、桩基检测。本发明能够提高车站出入口围护桩的施工效率,节约成本,施工的安全性高,使用广泛。
Construction method of entrance and exit fender posts
一种出入口围护桩的施工方法
YE MING (Autor:in) / CHEN DEQUAN (Autor:in) / ZHANG HAIWANG (Autor:in) / WANG HONGSONG (Autor:in) / HE JINXING (Autor:in) / RAO FEI (Autor:in) / CAO SHICHEN (Autor:in) / ZHAO YI (Autor:in) / ZHOU JIE (Autor:in) / YE ZHISHENG (Autor:in)
31.12.2021
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Device for constructing pipe shed on fender posts and construction method
Europäisches Patentamt | 2024
|Connecting joint of foundation pit prefabricated fender posts and construction method
Europäisches Patentamt | 2024
|Anchorage device for recycling main reinforcements of fender posts and construction method
Europäisches Patentamt | 2024
|Method for leaking stoppage between foundation pit fender posts
Europäisches Patentamt | 2021
|