Concrete pouring method for wind driven generator foundation under mountain conditions
The invention belongs to the technical field of wind power generation, and particularly discloses a concrete pouring method for a wind driven generator foundation under a mountain condition. The concrete pouring method comprises the following steps of preparing operation, specifically, preparing materials one day in advance by a mixing plant, and arranging a plurality of road passing track points on a mountain wind power plant; departing mixer trucks from a mixing plant, specifically, departing the mixer trucks from the mixing plant to the mountain wind power plant according to the time interval of 10-20 minutes; road transportation, specifically, according to the real-time position sharing information of all the mixer trucks and the principle of priority descending of empty trucks, enabling the trucks to be passed at the passing track point; and concrete pouring, specifically, unloading the concrete into the boom pump truck through the mixer trucks, and a wind driven generator foundation is poured through the boom pump truck. By combining arrangement of the passing track point and the real-time sharing of the positions of the mixer trucks, the traffic safety risk caused by vehicle transportation blockage on a mountain wind field road is avoided.
本发明属于风力发电技术领域,具体公开了一种山地条件下风力发电机基础的混凝土浇筑方法,包括以下步骤:作业准备,搅拌站提前一天备料,在山地风电场上设置若干道路错车点;搅拌站发车,按照10‑20分钟的时间间隔从搅拌站发车前往山地风电场;道路运输,根据所有搅拌车的实时位置共享信息,按照空车优先下行的原则,在错车点错车;混凝土浇筑,搅拌车将混凝土卸入天泵泵车,天泵泵车对风力发电机基础进行浇筑。通过将设置错车点与搅拌车位置实时共享结合,避免山地风场道路车辆运输堵路带来的交通安全风险。
Concrete pouring method for wind driven generator foundation under mountain conditions
The invention belongs to the technical field of wind power generation, and particularly discloses a concrete pouring method for a wind driven generator foundation under a mountain condition. The concrete pouring method comprises the following steps of preparing operation, specifically, preparing materials one day in advance by a mixing plant, and arranging a plurality of road passing track points on a mountain wind power plant; departing mixer trucks from a mixing plant, specifically, departing the mixer trucks from the mixing plant to the mountain wind power plant according to the time interval of 10-20 minutes; road transportation, specifically, according to the real-time position sharing information of all the mixer trucks and the principle of priority descending of empty trucks, enabling the trucks to be passed at the passing track point; and concrete pouring, specifically, unloading the concrete into the boom pump truck through the mixer trucks, and a wind driven generator foundation is poured through the boom pump truck. By combining arrangement of the passing track point and the real-time sharing of the positions of the mixer trucks, the traffic safety risk caused by vehicle transportation blockage on a mountain wind field road is avoided.
本发明属于风力发电技术领域,具体公开了一种山地条件下风力发电机基础的混凝土浇筑方法,包括以下步骤:作业准备,搅拌站提前一天备料,在山地风电场上设置若干道路错车点;搅拌站发车,按照10‑20分钟的时间间隔从搅拌站发车前往山地风电场;道路运输,根据所有搅拌车的实时位置共享信息,按照空车优先下行的原则,在错车点错车;混凝土浇筑,搅拌车将混凝土卸入天泵泵车,天泵泵车对风力发电机基础进行浇筑。通过将设置错车点与搅拌车位置实时共享结合,避免山地风场道路车辆运输堵路带来的交通安全风险。
Concrete pouring method for wind driven generator foundation under mountain conditions
一种山地条件下风力发电机基础的混凝土浇筑方法
LAI NINGJING (Autor:in) / ZHANG QI (Autor:in) / ZHANG QING (Autor:in) / PENG QIANG (Autor:in) / SUN ZHAOGUO (Autor:in) / HUANG CHUAN (Autor:in) / WANG BEN (Autor:in) / MIN YANG (Autor:in) / HUANG YAN (Autor:in) / HUANG YONG (Autor:in)
31.12.2021
Patent
Elektronische Ressource
Chinesisch
Concrete pouring device and raft foundation pouring method
Europäisches Patentamt | 2021
|Underwater pile foundation concrete pouring mold and concrete underwater pouring method thereof
Europäisches Patentamt | 2021
|