The invention relates to a beam section sliding installation construction method, which comprises the following steps of: pushing two ends of an oil cylinder to slide along a sliding rail, connecting a rear seat at the rear end of the oil cylinder, respectively rotationally connecting pull plates with hooks on two sides of the rear seat, arranging bayonets matched with the hooks on a rail foundation, clamping the hooks in the bayonets to provide counter force when the oil cylinder is pushed, and sliding the hooks out of the bayonets when the oil cylinder is contracted; when moving forwards, enabling the hooks to fall into a front bayonet, so that the oil cylinder moves forwards automatically; the track foundation is arranged to be of a multi-section combined structure, the rear sections move forwards alternately in the sliding process, and long-distance sliding of the beam section can be achieved through the short track foundation. The construction efficiency can be improved, and the construction cost can be reduced.
本发明涉及一种梁段滑移安装施工方法,采用油缸顶推两端沿滑轨滑移,在油缸后端连接一后座,后座两侧分别转动连接一带挂钩的拉板,轨道基础上设卡口与挂钩配合,油缸顶推时挂钩卡在卡口中提供反力,油缸收缩时挂钩先滑出卡口,前移时再落入前方卡口,实现油缸自动前行;轨道基础设置为多节段组合结构,滑移过程中将后方的节段交替前移,采用较短的轨道基础即可实现梁段长距离滑移。本发明能提高施工效率,降低施工成本。
Beam section sliding installation construction method
The invention relates to a beam section sliding installation construction method, which comprises the following steps of: pushing two ends of an oil cylinder to slide along a sliding rail, connecting a rear seat at the rear end of the oil cylinder, respectively rotationally connecting pull plates with hooks on two sides of the rear seat, arranging bayonets matched with the hooks on a rail foundation, clamping the hooks in the bayonets to provide counter force when the oil cylinder is pushed, and sliding the hooks out of the bayonets when the oil cylinder is contracted; when moving forwards, enabling the hooks to fall into a front bayonet, so that the oil cylinder moves forwards automatically; the track foundation is arranged to be of a multi-section combined structure, the rear sections move forwards alternately in the sliding process, and long-distance sliding of the beam section can be achieved through the short track foundation. The construction efficiency can be improved, and the construction cost can be reduced.
本发明涉及一种梁段滑移安装施工方法,采用油缸顶推两端沿滑轨滑移,在油缸后端连接一后座,后座两侧分别转动连接一带挂钩的拉板,轨道基础上设卡口与挂钩配合,油缸顶推时挂钩卡在卡口中提供反力,油缸收缩时挂钩先滑出卡口,前移时再落入前方卡口,实现油缸自动前行;轨道基础设置为多节段组合结构,滑移过程中将后方的节段交替前移,采用较短的轨道基础即可实现梁段长距离滑移。本发明能提高施工效率,降低施工成本。
Beam section sliding installation construction method
一种梁段滑移安装施工方法
HUANG ZHENWEI (Autor:in) / WANG ANWEN (Autor:in) / JIANG DELIN (Autor:in) / YU CE (Autor:in) / LI YE (Autor:in)
21.01.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E01D
BRIDGES
,
Brücken
Sliding installation method for large span section steel beam
Europäisches Patentamt | 2015
|Single-column pier steel cover beam sliding installation structure and construction method
Europäisches Patentamt | 2024
|Large-span box-type steel beam sliding installation construction process and device
Europäisches Patentamt | 2021
|