Box culvert settlement joint construction method
The invention relates to a construction method for a settlement joint of a box culvert. The construction method comprises the following steps: positioning and paying off; paying off on the plug template to determine the central position of the dowel bar, and then drilling according to the diameter of the dowel bar; reinforcing and mounting the steel-edged water-stop belt; the horizontal part of the steel edge water stop belt is reinforced and flattened; the machined dowel bar is installed in a hole position of a plug template, and the position of the dowel bar is adjusted; a dowel bar part on the outer side of the plug template is inserted into a sleeve of a dowel bar fixing frame, and then the dowel bar fixing frame is connected with the plug template through a drag hook; pouring concrete; mounting an embedded part; the embedded part is dismantled; sealing paste is used for crack pouring. According to the construction method, the construction quality problem of the steel edge water stop belt, the dowel bar and the sealant of the box culvert settlement joint is effectively solved through the matching effect of the reinforcing batten, the steel bar support, the dowel bar fixing frame and the shaping square steel, the construction method is simple in process and convenient to operate, manpower is saved, and the working efficiency is improved.
本发明涉及一种箱涵沉降缝施工方法,包括以下步骤:定位放线;在堵头模板上放线确定传力杆的中心位置,然后按照传力杆的直径进行钻孔;钢边止水带的加固安装;钢边止水带水平部位加固平展;将加工出来的传力杆安装到堵头模板的孔位中,调整传力杆的位置;将堵头模板外侧的传力杆部分插入传力杆固定架的套筒中,然后将传力杆固定架与堵头模板采用拉钩进行连接;混凝土浇筑;预埋件安装;预埋件拆除;密封膏灌缝。本发明通过加固木方、钢筋支架、传力杆固定架和定型方钢之间的配合作用,有效的解决了箱涵沉降缝的钢边止水带、传力杆和密封膏的施工质量问题,且本施工方法过程简单,操作方便,而且节省了人力,提高了工作效率。
Box culvert settlement joint construction method
The invention relates to a construction method for a settlement joint of a box culvert. The construction method comprises the following steps: positioning and paying off; paying off on the plug template to determine the central position of the dowel bar, and then drilling according to the diameter of the dowel bar; reinforcing and mounting the steel-edged water-stop belt; the horizontal part of the steel edge water stop belt is reinforced and flattened; the machined dowel bar is installed in a hole position of a plug template, and the position of the dowel bar is adjusted; a dowel bar part on the outer side of the plug template is inserted into a sleeve of a dowel bar fixing frame, and then the dowel bar fixing frame is connected with the plug template through a drag hook; pouring concrete; mounting an embedded part; the embedded part is dismantled; sealing paste is used for crack pouring. According to the construction method, the construction quality problem of the steel edge water stop belt, the dowel bar and the sealant of the box culvert settlement joint is effectively solved through the matching effect of the reinforcing batten, the steel bar support, the dowel bar fixing frame and the shaping square steel, the construction method is simple in process and convenient to operate, manpower is saved, and the working efficiency is improved.
本发明涉及一种箱涵沉降缝施工方法,包括以下步骤:定位放线;在堵头模板上放线确定传力杆的中心位置,然后按照传力杆的直径进行钻孔;钢边止水带的加固安装;钢边止水带水平部位加固平展;将加工出来的传力杆安装到堵头模板的孔位中,调整传力杆的位置;将堵头模板外侧的传力杆部分插入传力杆固定架的套筒中,然后将传力杆固定架与堵头模板采用拉钩进行连接;混凝土浇筑;预埋件安装;预埋件拆除;密封膏灌缝。本发明通过加固木方、钢筋支架、传力杆固定架和定型方钢之间的配合作用,有效的解决了箱涵沉降缝的钢边止水带、传力杆和密封膏的施工质量问题,且本施工方法过程简单,操作方便,而且节省了人力,提高了工作效率。
Box culvert settlement joint construction method
一种箱涵沉降缝施工方法
HE HONGLIE (Autor:in) / YANG YANG (Autor:in) / GAO JIANHUA (Autor:in) / XIE QINGHE (Autor:in) / DU YUNLONG (Autor:in) / WANG CONG (Autor:in) / PIATON (Autor:in) / FEI SIBO (Autor:in) / CHEN XIN (Autor:in) / KONG DEXI (Autor:in)
18.03.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
/
E02D
FOUNDATIONS
,
Gründungen
Box culvert settlement joint waterproof construction method
Europäisches Patentamt | 2021
|Reinforced concrete slab culvert fabricated settlement joint and construction method
Europäisches Patentamt | 2020
|Culvert settlement joint water seepage repairing structure and method for repairing settlement joint
Europäisches Patentamt | 2021
|Construction method for reserving asphalt board at settlement joint of drainage box culvert
Europäisches Patentamt | 2023
|Connecting method for waterproof settlement joint at junction of new box culvert and old box culvert
Europäisches Patentamt | 2022
|