Construction method for steel structure canopy roof curtain wall of transportation junction station
The invention discloses a construction method for a steel structure canopy roof curtain wall of a transportation junction station. The construction method comprises the following steps: S1, surveying and setting out; s2, checking whether the structure and the embedded part meet the mounting precision requirement of the curtain wall or not according to the surveying and setting-out result, and correcting; s3, the grid lines and the elevation lines of the connecting pieces are all bounced on the structure to serve as datum lines for installing the connecting pieces, and the steel connecting pieces are installed according to the center lines bounced by the paying-off sets and the grid lines; s4, the vertical keels are installed in a grid mode, and the transverse keels are installed according to the horizontal transverse lines; s5, the aluminum plate is installed on the keel frame through the pressing plate; and S6, after the aluminum plate is installed, plate joints are cleaned, the plate joints are filled with foam strips, and then gluing is conducted. The invention has the advantages of high installation precision and efficiency and capability of improving the overall appearance effect and the rainproof effect.
本发明公开了一种交通枢纽位站台钢结构雨棚屋面幕墙施工方法,包括以下步骤:S1:测量放线;S2:根据测量放线结果检查结构及预埋件是否符合幕墙的安装精度要求并做校正;S3:将连接件的分格线及标高线全部弹在结构上,作为安装连接件的基准线,依据放线组所弹中心线、分格线安装钢连接件;S4:将竖龙骨进行分格安装,依据水平横向线进行横龙骨的安装;S5:将铝板利用压板安装在龙骨框架上;S6:铝板安装完毕后,清理板缝,在板缝进行泡沫条填塞,再打胶。具有安装精度和效率高、可提高整体外观效果和防雨效果的优点。
Construction method for steel structure canopy roof curtain wall of transportation junction station
The invention discloses a construction method for a steel structure canopy roof curtain wall of a transportation junction station. The construction method comprises the following steps: S1, surveying and setting out; s2, checking whether the structure and the embedded part meet the mounting precision requirement of the curtain wall or not according to the surveying and setting-out result, and correcting; s3, the grid lines and the elevation lines of the connecting pieces are all bounced on the structure to serve as datum lines for installing the connecting pieces, and the steel connecting pieces are installed according to the center lines bounced by the paying-off sets and the grid lines; s4, the vertical keels are installed in a grid mode, and the transverse keels are installed according to the horizontal transverse lines; s5, the aluminum plate is installed on the keel frame through the pressing plate; and S6, after the aluminum plate is installed, plate joints are cleaned, the plate joints are filled with foam strips, and then gluing is conducted. The invention has the advantages of high installation precision and efficiency and capability of improving the overall appearance effect and the rainproof effect.
本发明公开了一种交通枢纽位站台钢结构雨棚屋面幕墙施工方法,包括以下步骤:S1:测量放线;S2:根据测量放线结果检查结构及预埋件是否符合幕墙的安装精度要求并做校正;S3:将连接件的分格线及标高线全部弹在结构上,作为安装连接件的基准线,依据放线组所弹中心线、分格线安装钢连接件;S4:将竖龙骨进行分格安装,依据水平横向线进行横龙骨的安装;S5:将铝板利用压板安装在龙骨框架上;S6:铝板安装完毕后,清理板缝,在板缝进行泡沫条填塞,再打胶。具有安装精度和效率高、可提高整体外观效果和防雨效果的优点。
Construction method for steel structure canopy roof curtain wall of transportation junction station
交通枢纽位站台钢结构雨棚屋面幕墙施工方法
CAO ZHENXING (Autor:in) / LI SHUCAI (Autor:in) / ZHOU HAO (Autor:in) / SHAO WEI (Autor:in) / LI YANG (Autor:in) / LONG GENWANG (Autor:in) / XIA ZHENRONG (Autor:in) / YAN ZHENWEI (Autor:in)
25.03.2022
Patent
Elektronische Ressource
Chinesisch
Europäisches Patentamt | 2022
|On-site splicing method for canopy hanging piece units of transportation junction station roof
Europäisches Patentamt | 2022
|On-site splicing method for Y-shaped column of transportation junction station roof canopy
Europäisches Patentamt | 2022
|Europäisches Patentamt | 2024
|Construction method of double-layer roof curtain wall structure
Europäisches Patentamt | 2021
|