Installation method of glass fiber reinforced plastic septic tank
The invention belongs to the field of glass fiber reinforced plastic septic tanks, and particularly relates to a glass fiber reinforced plastic septic tank mounting method which comprises the following steps: step 1, foundation pit earthwork excavation and disclosure construction related matters; secondly, a concrete cushion layer is cleaned and poured, and a foundation construction binding steel bar lofting formwork is poured; 3, hoisting the glass fiber reinforced plastic septic tank in a mechanical and manual combined hoisting mode; 4, performing layered backfilling: after the installation in place meets the requirements, filling water into the pool to exceed the underground water level to stabilize the pool, and enabling the compactness of backfilled soil to meet the related requirements; fifthly, the foundation face is washed, and a connecting well and an inspection well are built; sixthly, on-site preliminary acceptance inspection is carried out; through the installation method from the first step to the sixth step, the function of preventing the glass fiber reinforced plastic septic tank from settling or shifting after long time is achieved.
本发明属于玻璃钢化粪池领域,具体的说是一种玻璃钢化粪池的安装方法,该安装方法包括以下步骤:第一步:基坑土方挖掘,交底施工相关事宜;第二步:混凝土垫层清理浇筑,基础施工绑扎钢筋放样模板浇筑;第三步:玻璃钢化粪池吊装,使用机械和人工相结合的吊装方式;第四步:分层回填,安装就位符合要求之后,池内须注满水超过地下水位使之稳定,方可进行回填,回填土的密实度应达到相关要求;第五步:洗刷基础面筑砌连接井、检查井;第六步:现场初步验收;通过第一步到第六步的安装方法,实现了避免玻璃钢化粪池在长时间后产生沉降或偏移的功能。
Installation method of glass fiber reinforced plastic septic tank
The invention belongs to the field of glass fiber reinforced plastic septic tanks, and particularly relates to a glass fiber reinforced plastic septic tank mounting method which comprises the following steps: step 1, foundation pit earthwork excavation and disclosure construction related matters; secondly, a concrete cushion layer is cleaned and poured, and a foundation construction binding steel bar lofting formwork is poured; 3, hoisting the glass fiber reinforced plastic septic tank in a mechanical and manual combined hoisting mode; 4, performing layered backfilling: after the installation in place meets the requirements, filling water into the pool to exceed the underground water level to stabilize the pool, and enabling the compactness of backfilled soil to meet the related requirements; fifthly, the foundation face is washed, and a connecting well and an inspection well are built; sixthly, on-site preliminary acceptance inspection is carried out; through the installation method from the first step to the sixth step, the function of preventing the glass fiber reinforced plastic septic tank from settling or shifting after long time is achieved.
本发明属于玻璃钢化粪池领域,具体的说是一种玻璃钢化粪池的安装方法,该安装方法包括以下步骤:第一步:基坑土方挖掘,交底施工相关事宜;第二步:混凝土垫层清理浇筑,基础施工绑扎钢筋放样模板浇筑;第三步:玻璃钢化粪池吊装,使用机械和人工相结合的吊装方式;第四步:分层回填,安装就位符合要求之后,池内须注满水超过地下水位使之稳定,方可进行回填,回填土的密实度应达到相关要求;第五步:洗刷基础面筑砌连接井、检查井;第六步:现场初步验收;通过第一步到第六步的安装方法,实现了避免玻璃钢化粪池在长时间后产生沉降或偏移的功能。
Installation method of glass fiber reinforced plastic septic tank
一种玻璃钢化粪池的安装方法
ZHENG CHENGHUI (Autor:in) / ZHANG HUIZHONG (Autor:in) / CHU XULIANG (Autor:in) / WANG FUWEI (Autor:in)
15.04.2022
Patent
Elektronische Ressource
Chinesisch
Construction method of glass fiber reinforced plastic septic tank
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2023
|Chimney glass fiber reinforced plastic inner tube fast installation method
Europäisches Patentamt | 2015
|Reinforced concrete septic tank and hoisting method thereof
Europäisches Patentamt | 2023
|