Imbricated reinforced concrete chute construction process
The invention discloses an imbricated reinforced concrete torrent chute construction process which comprises the following steps: measuring and setting out: measuring torrent chute construction data, and calculating the required construction material amount; site construction is conducted, specifically, a torrent groove construction site is pretreated; installation of the torrent tank: installing a construction material in the pretreated torrent tank construction site; construction of a torrent groove water inlet: constructing a torrent groove inlet structure; checking and accepting: detecting parameters of the torrent chute after construction. According to the construction technology of the imbricated reinforced concrete torrent groove, the torrent groove is prefabricated and installed through reinforced concrete, the problem that roadbed slope water damage is caused by water leakage of a mortar rubble torrent groove can be effectively solved, the torrent groove is prefabricated in a factory and is assembled after being transported to a site, the section is semicircular, and the torrent groove is formed. The requirements for construction and durability are met in the form of reinforced concrete, the working labor intensity can be effectively reduced, materials are convenient to transport, concrete cracks are avoided, and the engineering quality is guaranteed.
本发明公开了一种叠瓦式钢筋混凝土急流槽施工工艺,包括以下步骤,测量放样:测量急流槽施工数据,并且计算需要的施工材料量;场地施工:对急流槽施工场地进行预处理;急流槽安装:向预处理后的急流槽施工场地中安装施工材料;急流槽入水口施工:施工急流槽进口结构;验收:检测施工后急流槽参数。本发明所述的一种叠瓦式钢筋混凝土急流槽施工工艺,采用钢筋混凝土预制安装急流槽能有效防止浆砌片石急流槽易出现的渗漏水造成路基边坡水损害问题,在工厂预制,运输到现场后组装,断面形式采用半圆形,通过配筋混凝土的形式满足构造和耐久性的要求,还能够有效降低工作劳动强度、材料运输方便、避免混凝土裂缝、保证工程质量。
Imbricated reinforced concrete chute construction process
The invention discloses an imbricated reinforced concrete torrent chute construction process which comprises the following steps: measuring and setting out: measuring torrent chute construction data, and calculating the required construction material amount; site construction is conducted, specifically, a torrent groove construction site is pretreated; installation of the torrent tank: installing a construction material in the pretreated torrent tank construction site; construction of a torrent groove water inlet: constructing a torrent groove inlet structure; checking and accepting: detecting parameters of the torrent chute after construction. According to the construction technology of the imbricated reinforced concrete torrent groove, the torrent groove is prefabricated and installed through reinforced concrete, the problem that roadbed slope water damage is caused by water leakage of a mortar rubble torrent groove can be effectively solved, the torrent groove is prefabricated in a factory and is assembled after being transported to a site, the section is semicircular, and the torrent groove is formed. The requirements for construction and durability are met in the form of reinforced concrete, the working labor intensity can be effectively reduced, materials are convenient to transport, concrete cracks are avoided, and the engineering quality is guaranteed.
本发明公开了一种叠瓦式钢筋混凝土急流槽施工工艺,包括以下步骤,测量放样:测量急流槽施工数据,并且计算需要的施工材料量;场地施工:对急流槽施工场地进行预处理;急流槽安装:向预处理后的急流槽施工场地中安装施工材料;急流槽入水口施工:施工急流槽进口结构;验收:检测施工后急流槽参数。本发明所述的一种叠瓦式钢筋混凝土急流槽施工工艺,采用钢筋混凝土预制安装急流槽能有效防止浆砌片石急流槽易出现的渗漏水造成路基边坡水损害问题,在工厂预制,运输到现场后组装,断面形式采用半圆形,通过配筋混凝土的形式满足构造和耐久性的要求,还能够有效降低工作劳动强度、材料运输方便、避免混凝土裂缝、保证工程质量。
Imbricated reinforced concrete chute construction process
一种叠瓦式钢筋混凝土急流槽施工工艺
LI FENGYUAN (Autor:in) / LI XIAODONG (Autor:in) / LIU JIANWEI (Autor:in) / CHENG QIANG (Autor:in) / SONG HAIPU (Autor:in) / DONG YUEXIA (Autor:in) / CHENG XIAOPANG (Autor:in) / ZHAO GUOWEI (Autor:in) / ZHANG TIANXI (Autor:in)
29.07.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02B
HYDRAULIC ENGINEERING
,
Wasserbau
Imbricated stone curtain wall structure and construction method thereof