Municipal road kerb prefabrication and installation construction method
The invention relates to the technical field of municipal road curb prefabrication and installation, in particular to a municipal road curb prefabrication and installation construction method which comprises the following steps of area division, mold installation, prefabrication pouring, transportation forming, maintenance demolding and hoisting construction. The construction method has the beneficial effects that the pouring and vibrating platform and the moving trolley are arranged on a construction site for transportation, so that single curbs are poured and transported in time, the curbs are arranged on the two sides of a road after the pouring process and are statically solidified and formed, accumulation of the curbs is greatly reduced, and the construction efficiency is improved. And meanwhile, long-distance transportation of the curbs in the construction process is avoided, the purposes of automatic maintenance and timing demolding are achieved by arranging a timing device and a watering maintenance device on the mold, and therefore recycling of the mold is achieved.
本发明涉及市政道路路缘石的预制安装技术领域,具体为市政道路路缘石预制安装施工方法,施工方法包含以下步骤:区域划分、模具安装、预制浇筑、运输成型、养护脱模和吊装施工,有益效果为:通过在施工现场设置浇筑振捣平台和移动小车的运输,实现对单一的路缘石进行浇筑和及时运输,使得浇筑过程后的路缘石在道路的两侧排列,并静止凝固成型,大大减小了对路缘石的堆积,同时避免在施工过程中对路缘石进行长距离运输,通过在模具上设置定时装置和洒水养护装置,实现自动养护和计时脱模的目的,从而实现模具的循环使用。
Municipal road kerb prefabrication and installation construction method
The invention relates to the technical field of municipal road curb prefabrication and installation, in particular to a municipal road curb prefabrication and installation construction method which comprises the following steps of area division, mold installation, prefabrication pouring, transportation forming, maintenance demolding and hoisting construction. The construction method has the beneficial effects that the pouring and vibrating platform and the moving trolley are arranged on a construction site for transportation, so that single curbs are poured and transported in time, the curbs are arranged on the two sides of a road after the pouring process and are statically solidified and formed, accumulation of the curbs is greatly reduced, and the construction efficiency is improved. And meanwhile, long-distance transportation of the curbs in the construction process is avoided, the purposes of automatic maintenance and timing demolding are achieved by arranging a timing device and a watering maintenance device on the mold, and therefore recycling of the mold is achieved.
本发明涉及市政道路路缘石的预制安装技术领域,具体为市政道路路缘石预制安装施工方法,施工方法包含以下步骤:区域划分、模具安装、预制浇筑、运输成型、养护脱模和吊装施工,有益效果为:通过在施工现场设置浇筑振捣平台和移动小车的运输,实现对单一的路缘石进行浇筑和及时运输,使得浇筑过程后的路缘石在道路的两侧排列,并静止凝固成型,大大减小了对路缘石的堆积,同时避免在施工过程中对路缘石进行长距离运输,通过在模具上设置定时装置和洒水养护装置,实现自动养护和计时脱模的目的,从而实现模具的循环使用。
Municipal road kerb prefabrication and installation construction method
市政道路路缘石预制安装施工方法
ZHOU BIAO (Autor:in) / DING CHUNLI (Autor:in)
09.08.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E01C
Bau von Straßen, Sportplätzen oder dgl., Decken dafür
,
CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE
Municipal road curb stone prefabrication and installation construction method
Europäisches Patentamt | 2020
|Municipal kerb construction method and use method thereof
Europäisches Patentamt | 2021
|