Installation method for steep slope roof tiles of pseudo-classic architecture
The invention discloses a mounting method for steep slope roof tiles of a pseudo-classic building. The mounting method comprises the steps that S1, firstly, a reinforced concrete main body structure of a roof is constructed; s2, anti-skid steel bars are implanted according to the design parameters; s3, reinforcing mesh pieces are bound, and the distance between the reinforcing mesh pieces is set based on the tile pieces of the roof; s4, after binding of the reinforcing mesh is completed, the anti-skid reinforcing steel bars implanted in advance are bent to the reinforcing mesh, and it is ensured that the anti-skid reinforcing steel bar bent anchors are effectively connected with the mesh; s5, binding copper wires on the reinforcing mesh, and reserving the copper wires; s6, the bottom tiles are installed firstly, and then the cylindrical tiles are installed; construction is conducted from bottom to top in sequence, and construction is conducted from the cornice dripping tiles and the bottom tile tiles to the top of the roof; s7, after construction of the bottom tile piece is completed, the cylindrical tile is started to be constructed, and the flower eave tile piece and the cylindrical tile piece are sequentially laid from bottom to top; and S8, after construction of the bottom tiles and the cylindrical tiles is completed, multi-layer ridges of the roof are started to be constructed, and therefore installation of the whole roof tiles is completed.
本发明公开了一种仿古建筑陡坡屋面瓦的安装方法,包括:S1:首先进行屋面的钢筋混凝土主体结构施工;S2:依据设计参数植入防滑钢筋;S3:绑扎钢筋网片,钢筋网片的间距基于屋面各瓦件设置;S4:在钢筋网片绑扎完成后,将提前植入的防滑钢筋弯折到钢筋网片上,确保防滑钢筋弯锚与网进行有效链接;S5:在钢筋网片上绑扎铜丝,进行铜丝预留;S6:按照先安装底瓦再安装筒瓦的顺序进行;铺贴顺序采用从下往上顺序依次施工,从檐口滴水瓦件、底瓦瓦件开始向屋面的顶部施工;S7:在底瓦瓦件施工完成后开始施工筒瓦,顺序从下往上依次铺设花檐瓦件和筒瓦瓦件;S8:在底瓦和筒瓦施工完成后,开始施工屋面的千层屋脊,从而完成整个屋面瓦的安装。
Installation method for steep slope roof tiles of pseudo-classic architecture
The invention discloses a mounting method for steep slope roof tiles of a pseudo-classic building. The mounting method comprises the steps that S1, firstly, a reinforced concrete main body structure of a roof is constructed; s2, anti-skid steel bars are implanted according to the design parameters; s3, reinforcing mesh pieces are bound, and the distance between the reinforcing mesh pieces is set based on the tile pieces of the roof; s4, after binding of the reinforcing mesh is completed, the anti-skid reinforcing steel bars implanted in advance are bent to the reinforcing mesh, and it is ensured that the anti-skid reinforcing steel bar bent anchors are effectively connected with the mesh; s5, binding copper wires on the reinforcing mesh, and reserving the copper wires; s6, the bottom tiles are installed firstly, and then the cylindrical tiles are installed; construction is conducted from bottom to top in sequence, and construction is conducted from the cornice dripping tiles and the bottom tile tiles to the top of the roof; s7, after construction of the bottom tile piece is completed, the cylindrical tile is started to be constructed, and the flower eave tile piece and the cylindrical tile piece are sequentially laid from bottom to top; and S8, after construction of the bottom tiles and the cylindrical tiles is completed, multi-layer ridges of the roof are started to be constructed, and therefore installation of the whole roof tiles is completed.
本发明公开了一种仿古建筑陡坡屋面瓦的安装方法,包括:S1:首先进行屋面的钢筋混凝土主体结构施工;S2:依据设计参数植入防滑钢筋;S3:绑扎钢筋网片,钢筋网片的间距基于屋面各瓦件设置;S4:在钢筋网片绑扎完成后,将提前植入的防滑钢筋弯折到钢筋网片上,确保防滑钢筋弯锚与网进行有效链接;S5:在钢筋网片上绑扎铜丝,进行铜丝预留;S6:按照先安装底瓦再安装筒瓦的顺序进行;铺贴顺序采用从下往上顺序依次施工,从檐口滴水瓦件、底瓦瓦件开始向屋面的顶部施工;S7:在底瓦瓦件施工完成后开始施工筒瓦,顺序从下往上依次铺设花檐瓦件和筒瓦瓦件;S8:在底瓦和筒瓦施工完成后,开始施工屋面的千层屋脊,从而完成整个屋面瓦的安装。
Installation method for steep slope roof tiles of pseudo-classic architecture
一种仿古建筑陡坡屋面瓦的安装方法
WANG XUDONG (Autor:in) / LIU TAO (Autor:in) / LIU YU (Autor:in) / WANG QI (Autor:in)
26.08.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E04D
ROOF COVERINGS
,
Dacheindeckungen
Mounting and reinforcing method for pseudo-classic building roof slope metal plate tiles
Europäisches Patentamt | 2022
|Roof eave gutter structure of pseudo-classic architecture
Europäisches Patentamt | 2024
|Pseudo-classic architecture roof and construction process thereof
Europäisches Patentamt | 2021
|