Dome glass curtain wall construction method
The invention belongs to the field of glass curtain wall installation, and relates to a dome glass curtain wall construction method which comprises the following steps: determining the circle center of a dome; calculating the size by software; a scaffold used for measuring and paying off is erected, steel keels are equally divided into 32 parts according to a drawing by means of the determined circle center and an original steel structure, the center line of each keel is determined, fine adjustment is conducted, and it is ensured that each keel is evenly stressed; overlapping the steel skeleton; spraying the surface; and glass installation is conducted, specifically, the cut aluminum profile and the glass plate are bonded together through a silicone weather-proof structural sealant, after the structural sealant reaches the constructable strength, a glass surface layer and a steel keel are fixed through an aluminum profile pressing block, and after the glass plate is installed and qualified, gluing treatment is conducted. Compared with an existing common construction technology, the construction technology is faster, the construction period can be shortened, the construction cost can be reduced, plasticity is better, safety is good, and industry development is promoted.
本发明属于玻璃幕墙安装领域,涉及穹顶玻璃幕墙施工方法,它包括以下步骤:确定穹顶圆心;软件计算尺寸;放线:搭设用于测量放线的脚手架,按照图纸利用确定好的圆心和原有的钢结构将钢龙骨等分成32份,并确定每根龙骨的中心线,并进行微调,确保每根龙骨的受力均匀;钢骨架搭接;表面喷涂;玻璃安装:将切割完成的铝型材利用硅酮耐候结构密封胶与玻璃板块粘接在一起,待结构胶达到可施工强度后,利用铝型材压块将玻璃面层与钢龙骨进行固定,玻璃板块安装完成经验收合格后,进行打胶处理。本发明相对于现有普通施工技术,施工工艺更加快捷,可缩短施工周期,降低施工成本,可塑性更好,安全性好,促进行业的发展。
Dome glass curtain wall construction method
The invention belongs to the field of glass curtain wall installation, and relates to a dome glass curtain wall construction method which comprises the following steps: determining the circle center of a dome; calculating the size by software; a scaffold used for measuring and paying off is erected, steel keels are equally divided into 32 parts according to a drawing by means of the determined circle center and an original steel structure, the center line of each keel is determined, fine adjustment is conducted, and it is ensured that each keel is evenly stressed; overlapping the steel skeleton; spraying the surface; and glass installation is conducted, specifically, the cut aluminum profile and the glass plate are bonded together through a silicone weather-proof structural sealant, after the structural sealant reaches the constructable strength, a glass surface layer and a steel keel are fixed through an aluminum profile pressing block, and after the glass plate is installed and qualified, gluing treatment is conducted. Compared with an existing common construction technology, the construction technology is faster, the construction period can be shortened, the construction cost can be reduced, plasticity is better, safety is good, and industry development is promoted.
本发明属于玻璃幕墙安装领域,涉及穹顶玻璃幕墙施工方法,它包括以下步骤:确定穹顶圆心;软件计算尺寸;放线:搭设用于测量放线的脚手架,按照图纸利用确定好的圆心和原有的钢结构将钢龙骨等分成32份,并确定每根龙骨的中心线,并进行微调,确保每根龙骨的受力均匀;钢骨架搭接;表面喷涂;玻璃安装:将切割完成的铝型材利用硅酮耐候结构密封胶与玻璃板块粘接在一起,待结构胶达到可施工强度后,利用铝型材压块将玻璃面层与钢龙骨进行固定,玻璃板块安装完成经验收合格后,进行打胶处理。本发明相对于现有普通施工技术,施工工艺更加快捷,可缩短施工周期,降低施工成本,可塑性更好,安全性好,促进行业的发展。
Dome glass curtain wall construction method
穹顶玻璃幕墙施工方法
MIAO FENG (Autor:in) / WEI PENGFEI (Autor:in) / XING ZHENJIN (Autor:in) / ZHANG MIN (Autor:in) / QI WEI (Autor:in) / WANG JIN (Autor:in) / GUO YUFENG (Autor:in) / SHAO SUISHENG (Autor:in) / WANG XIAMENG (Autor:in) / WANG JIANZHEN (Autor:in)
16.09.2022
Patent
Elektronische Ressource
Chinesisch
Installation method of dome structure glass curtain wall
Europäisches Patentamt | 2023
|Glass curtain wall construction method and glass curtain wall structure
Europäisches Patentamt | 2023
|