Temporary filling construction method for underground diaphragm wall joint
The invention discloses an underground diaphragm wall joint temporary filling construction method which comprises the following steps: a, pore-forming detection: b, filling bag installation: arranging square timbers on two sides of a guide wall in a groove body, putting the filling bag into the groove, ensuring that the height difference between the top of the filling bag and the ground is within positive 1m and negative 0.5 m, and meanwhile, ensuring that the filling bag is exposed out of the liquid level; when the top of the filling bag exceeds 1 meter, the filling bag must be hoisted by a special frame to ensure that the filling bag is in a natural vertical state; c, pipeline connection: communicating the pipelines among the water source, the complete set of loading monitoring equipment and the filling bag; and d, loading and monitoring the filling bag. The filling device has the advantages of being simple in structure, high in strength, high in operability and good in filling effect.
本发明公开了一种地连墙接头临时填充施工方法,包括以下步骤:a、成孔探测:b、填充囊安装:在槽体内导墙两侧设置方木,将填充囊放入槽内,确保填充囊顶部与地面高低差在正1米、负0.5米之内,同时保证填充囊露出液面,当填充囊顶部超出1米时必须使用专用架吊起,保证填充囊在自然垂直状态;c、管道连接:将水源、成套加载监控设备和填充囊之间的管路连通;d、填充囊加载以及监控。本发明具有结构简单、强度高,操作性强、填充效果好的优点。
Temporary filling construction method for underground diaphragm wall joint
The invention discloses an underground diaphragm wall joint temporary filling construction method which comprises the following steps: a, pore-forming detection: b, filling bag installation: arranging square timbers on two sides of a guide wall in a groove body, putting the filling bag into the groove, ensuring that the height difference between the top of the filling bag and the ground is within positive 1m and negative 0.5 m, and meanwhile, ensuring that the filling bag is exposed out of the liquid level; when the top of the filling bag exceeds 1 meter, the filling bag must be hoisted by a special frame to ensure that the filling bag is in a natural vertical state; c, pipeline connection: communicating the pipelines among the water source, the complete set of loading monitoring equipment and the filling bag; and d, loading and monitoring the filling bag. The filling device has the advantages of being simple in structure, high in strength, high in operability and good in filling effect.
本发明公开了一种地连墙接头临时填充施工方法,包括以下步骤:a、成孔探测:b、填充囊安装:在槽体内导墙两侧设置方木,将填充囊放入槽内,确保填充囊顶部与地面高低差在正1米、负0.5米之内,同时保证填充囊露出液面,当填充囊顶部超出1米时必须使用专用架吊起,保证填充囊在自然垂直状态;c、管道连接:将水源、成套加载监控设备和填充囊之间的管路连通;d、填充囊加载以及监控。本发明具有结构简单、强度高,操作性强、填充效果好的优点。
Temporary filling construction method for underground diaphragm wall joint
地连墙接头临时填充施工方法
PENG WEI (Autor:in) / DUAN CHANGHENG (Autor:in) / LI CHANGQIN (Autor:in) / GUO KECHENG (Autor:in)
25.10.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
Underground diaphragm wall joint filling anti-streaming construction method
Europäisches Patentamt | 2024
|Underground diaphragm wall joint and construction method of underground diaphragm wall
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2020
|Construction method of underground diaphragm wall and butt joint of underground diaphragm wall
Europäisches Patentamt | 2020
|