High, steep and strong unloading water slope excavation slag collecting platform and construction method thereof
According to the high, steep and strong unloading water slope excavation slag collecting platform and the construction method thereof, an existing gully of the water slope is used as a slag sliding channel in the excavation process, and the slag collecting platform is formed above the water surface of the bottom of the water slope through local excavation and construction of a steel structure platform; the slag collecting platform is arranged at the slope bottom of the overwater slope and covers the multiple slag sliding channels in the longitudinal total length direction; the overwater steel structure platform depends on a local excavation platform of the overwater side slope through the supporting system and is overhung towards the outer side of the overwater side slope, and the bottom of the supporting system on the lower portion of the overhanging part of the overwater steel structure platform penetrates into the underwater side slope and is fixed. A protection structure is arranged on the outer side of the water steel structure platform. The problems that the construction difficulty of a slope surface construction road of the high and steep and strong unloading slope is large, potential safety hazards are large, and river channels are blocked and water bodies are polluted due to falling of slag adhering to the slope surface in the slope excavation process are solved.
本发明提供了高陡、强卸荷水上边坡开挖集渣平台及其施工方法,利用水上边坡现有的冲沟作为开挖过程中的溜渣通道,在水上边坡的底部水面以上通过局部开挖和修建钢结构平台形成一个集渣平台,所述集渣平台设置在水上边坡的坡底部且纵向总长度覆盖多个溜渣通道;所述水上钢结构平台通过支撑体系依靠水上边坡的局部开挖平台,并向水上边坡的外侧悬挑,水上钢结构平台悬挑部分的下部支撑体系底部深入水下边坡并固定;所述水上钢结构平台的外侧设置防护结构。本发明解决了高陡、强卸荷边坡坡面施工道路修建难度大、安全隐患大以及边坡开挖过程中坡面挂渣掉落引起的阻塞河道、污染水体的问题。
High, steep and strong unloading water slope excavation slag collecting platform and construction method thereof
According to the high, steep and strong unloading water slope excavation slag collecting platform and the construction method thereof, an existing gully of the water slope is used as a slag sliding channel in the excavation process, and the slag collecting platform is formed above the water surface of the bottom of the water slope through local excavation and construction of a steel structure platform; the slag collecting platform is arranged at the slope bottom of the overwater slope and covers the multiple slag sliding channels in the longitudinal total length direction; the overwater steel structure platform depends on a local excavation platform of the overwater side slope through the supporting system and is overhung towards the outer side of the overwater side slope, and the bottom of the supporting system on the lower portion of the overhanging part of the overwater steel structure platform penetrates into the underwater side slope and is fixed. A protection structure is arranged on the outer side of the water steel structure platform. The problems that the construction difficulty of a slope surface construction road of the high and steep and strong unloading slope is large, potential safety hazards are large, and river channels are blocked and water bodies are polluted due to falling of slag adhering to the slope surface in the slope excavation process are solved.
本发明提供了高陡、强卸荷水上边坡开挖集渣平台及其施工方法,利用水上边坡现有的冲沟作为开挖过程中的溜渣通道,在水上边坡的底部水面以上通过局部开挖和修建钢结构平台形成一个集渣平台,所述集渣平台设置在水上边坡的坡底部且纵向总长度覆盖多个溜渣通道;所述水上钢结构平台通过支撑体系依靠水上边坡的局部开挖平台,并向水上边坡的外侧悬挑,水上钢结构平台悬挑部分的下部支撑体系底部深入水下边坡并固定;所述水上钢结构平台的外侧设置防护结构。本发明解决了高陡、强卸荷边坡坡面施工道路修建难度大、安全隐患大以及边坡开挖过程中坡面挂渣掉落引起的阻塞河道、污染水体的问题。
High, steep and strong unloading water slope excavation slag collecting platform and construction method thereof
高陡、强卸荷水上边坡开挖集渣平台及其施工方法
ZHU ANLONG (Autor:in) / WANG RUI (Autor:in) / XU DECAO (Autor:in) / PENG FEI (Autor:in)
01.11.2022
Patent
Elektronische Ressource
Chinesisch
IPC:
E02D
FOUNDATIONS
,
Gründungen
/
E01F
ADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
,
Zusätzliche Baumaßnahmen, wie die Ausstattung von Straßen oder die bauliche Ausbildung von Bahnsteigen, Landeplätzen für Hubschrauber, Wegweisern, Schneezäunen oder dgl.
Slag collecting platform safety protection device for high and steep slope excavation
Europäisches Patentamt | 2024
|Stability analysis of high and steep slope considering excavation unloading effect
British Library Conference Proceedings | 2010
|High and steep slope excavation pre-supporting device and excavation method
Europäisches Patentamt | 2024
|Slope excavation construction method under steep and severe geological conditions
Europäisches Patentamt | 2023
|